Item Coversheet
Back

Item Coversheet


CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 4/5/2022
District D, District G
Item Creation Date: 2/24/2022

HPW – 20EN71 Contract Award / Industrial TX Corp.

Agenda Item#:


 
                               
Summary:

ORDINANCE appropriating $23,393,000.00 out of Water & Sewer System Consolidated Construction Fund; awarding contract to INDUSTRIAL TX CORP for Lift Station Renewal and Replacement; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for CIP Cost Recovery relating to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund - DISTRICTS D - EVANS-SHABAZZ and G - HUFFMAN

Background:

SUBJECT: Contract Award for Lift Station Renewal and Replacement.

 

RECOMMENDATION: Award a Construction Contract to Industrial TX Corp. for Lift Station Renewal and Replacement and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the City’s ongoing program to upgrade its wastewater lift station facilities.

 

The work to be performed under this contract award is necessary to maintain compliance with Houston's wastewater consent decree with EPA and TCEQ.

 

DESCRIPTION/SCOPE: This project consists of the replacement of Magnet lift station and rehabilitation of Westpark No. 1 and MacGregor Way North No. 1 lift stations. The rehabilitation includes site work, pumps, piping, valves, support, instrumentation and electrical improvements.  The Contract duration for this project is 550 calendar days. This project was designed by CP&Y, Inc.

 

LOCATION: The project locations are:

 

Lift Station

Location / Address

Council District

MacGregor Way North No. 1

2000 North MacGregor Way

D

Magnet

2710 Magnet Street

D

Westpark No. 1

4307 Westpark Drive

G

 

BIDS: This project was advertised for bidding on December 3, 2021. Bids were received on January 20, 2022.  The one (1) bid is as follows:

 

 

Bidder

Bid Amount

1.

Industrial TX Corp.

$21,029,950.00

 

AWARD: It is recommended that this construction contract be awarded to Industrial TX Corp. with a low bid of $21,029,950.00 and Addenda Numbers 1 and 2 be made a part of this Contract.

 

PROJECT COST: The total cost of this project is $23,393,000.00 to be appropriated as follows:

 

Bid Amount

$21,029,950.00

Contingencies

$  1,051,497.50

Testing Services

$     260,000.00

CIP Cost Recovery

$  1,051,552.50

 

Testing Services will be provided by Associated Testing Laboratories, Inc. under a previously approved contract.

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case, Industrial TX Corp. is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides benefits for some employees but will pay into the Contractor Responsibility Fund for others, in compliance with City policy.

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 11% MBE goal and 7% WBE goal for this project.

 

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

Sustanite Support Services, LLC, DBA S3

Mechanical piping

$    800,000.00

3.80%

2.

Aviles Painting Contractor

Painting

$    175,000.00

0.83%

3.

Magna-Flow International, Inc., DBA Magna-Flow

Environmental

Sludge collection

$      70,000.00

0.33%

4.

Ace Controls, LLC

Water, wastewater process, and automation control

$    745,000.00

3.54%

5.

C & B Rebar Construction, Inc.

Rebar contractor

$      90,000.00

____________

0.43%

_____

 

 

TOTAL

$ 1,880,000.00

8.94%

 

 

WBE - Name of Firms

Work Description

Amount

% of Contract

1.

Bevco Company, Inc.

Plumbing supplies

$   416,000.00

1.98%

2.

F & L Coatings And Concrete, L.L.C.

Protective coatings and grout abandonment

$   682,156.00

3.24%

3.

Macaulay Controls Company

Process control instruments

$   205,598.00

0.98%

4.

Holes Incorporated

Break concrete

$   139,011.00

0.66%

 

 

TOTAL

$1,442,765.00

6.86%

 

 

SBE - Name of Firms

Work Description

Amount

% of Contract

1.

Automation Nation, Inc.

Automation controls

$     34,000.00

0.16%

2.

Medcalf Fabrication, Inc.

Miscellaneous metals

$   554,505.00

2.64%

 

 

TOTAL

$   588,505.00

2.80%

 

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

All known rights-of-way, easements and/or right-of-entry required for the project have been acquired.

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. R-000267-0118-4

Prior Council Action:
Amount and Source of Funding:

$23,393,000.00

 Water and Sewer System Consolidated Construction Fund

 Fund No. 8500

Contact Information:

R. Jeff Masek, P.E., CCM

Assistant Director, Capital Projects

Houston Public Works Department

Phone: (832) 395-2387

ATTACHMENTS:
DescriptionType
MapsBackup Material