Item Coversheet
Back

Item Coversheet


CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 11/8/2017
District G
Item Creation Date: 8/15/2017

20RH04 Contract Award / SER Construction Partners

Agenda Item#:


 
                               
Summary:

ORDINANCE appropriating $6,350,000.00 out of Street & Traffic Control and Storm Drainage DDSRF awarding contract to SER CONSTRUCTION PARTNERS, LLC. for Yorkshire Area Drainage and Paving Improvements; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for Testing, CIP Cost Recovery, Construction Management, and Contingencies relating to construction of facilities financed by the Street & Traffic Control and Storm Drainage DDSRF - DISTRICT G - TRAVIS

Background:

SUBJECT: Contract Award for Yorkshire Area Drainage and Paving Improvements, WBS Nos. M-000247-0002-4.

 

 RECOMMENDATION: (SUMMARY)

Accept low bid, award Construction Contract and appropriate funds.

 

 PROJECT NOTICE/JUSTIFICATION: This project is part of the Capital Improvements Program (CIP) and is required to resolve inadequate drainage system and reduce the potential for structural flooding.

DESCRIPTION/SCOPE: This project consists of construction of storm drainage improvements, necessary concrete paving, curbs, sidewalks, driveways and underground utilities. The Contract duration for this project is 420 calendar days. This project was designed by CivilTech Engineering, Inc.

LOCATION: The project area is generally bound by Memorial Drive on the north, Buffalo Bayou on the south, Regentview Street on the east and Kirkwood Road on the west.  The project is located in Key Map Grids 489 E & F.

BIDS: This project was advertised for bidding on May 27, 2017. Bids were received on June 22, 2017.  The five (5) bids are as follows:

 

                         Bidder                                                               Bid Amount

1.

SER Construction Partners, LLC

$5,291,584.60

2.

Total Contracting Limited

$5,439,683.30

3.

Resicom, Inc.

$5,608,633.80

4.

Reytec Construction Resources, Inc

$5,682,988.50

5.

Harper Brothers Construction, LLC

$6,077,239.00

   

AWARD: It is recommended that this construction contract be awarded to SER Construction Partners, LLC with a low bid of $5,291,584.60 and Addendum Numbers 1 and 2 be made a part of this Contract.

 

 PROJECT COST: The total cost of this project is $6,350,000.00 to be appropriated as follows:

 

· Bid Amount

$5,291,584.60

· Contingencies

$264,600.00

· Testing Services

$175,000.00

· CIP Cost Recovery

$218,815.40

· Construction Management

$400,000.00

 

 Testing Services will be provided by Professional Service Industries, Inc. under a previously approved contract.

 

Construction Management Services will be provided by TLC Engineering, Inc. under a previously approved contract.

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case SER Construction Partners, LLC is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 11 % MBE goal and 7% WBE goal for this project.

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

Reliable Signal & Lightning Solutions, LLC

Electrical

$ 122,500.00

2.31%

 

2.

 

PRV Services, Inc.

 

Concrete Paving

 

$ 164,500.00

 

3.11%

         
3.

Bedo Construction Products, Inc.

Supply Pipe Products

$ 295,500.00

5.58%

 

 

TOTAL

$ 582,500.00

11.00%

 

 

WBE - Name of Firms

Work Description

Amount

% of Contract

1.

Deanie Hayes, Inc.

Supply Stabilized Sand

$ 180,000.00

3.40%

 

 

TOTAL

$ 180,000.00

3.40%

 

 

SBE - Name of Firms

Work Description

Amount

% of Contract

1.

Semarck Landscape Services, Inc.

Landscaping

$ 194,500.00

3.68%

 

 

TOTAL

$ 194,500.00

3.68%

 

ESTIMATED FISCAL OPERATING IMPACT:

No significant Fiscal Operating impact is anticipated as a result of this project.

 

All known rights-of-way, easements and/or right-of-entry required for the project have been acquired.

 

 

 

_________________________________

Carol Ellinger Haddock, P.E.

Acting Director

Department of Public Works and Engineering

 

WBS No. M-000247-0002-4


Prior Council Action:
Amount of Funding:

$6,350,000.00 - Fund No. 4042-Street & Traffic Control and Storm Drainage DDSRF

($6,350,000.00 Supported by Drainage Fee)
Contact Information:

Brian Alcott, P.E.

Acting Senior Assistant Director, Capital Projects

Phone: (832) 395-2396


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material