CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/6/2016
District A
Item Creation Date: 9/12/2016

20CAH01 Add'tl Approp/CivilTech

Agenda Item#: 56.


 
                               
Summary:

ORDINANCE appropriating $1,339,000.00 out of Street & Traffic Control and Storm Drainage DDSRF as an additional appropriation to Professional Engineering Services Contract between the City of Houston and CIVILTECH ENGINEERING, INC for Spring Shadows (North) Drainage and Paving (Approved by Ordinance No. 2014-0551); providing funding for CIP Cost Recovery relating to construction of facilities financed by the Street & Traffic Control and Storm Drainage DDSRF - DISTRICT A - STARDIG

TAGGED BY COUNCIL MEMBER STARDIG

This was Item 41 on Agenda of November 30, 2016

Background:

SUBJECT:  Additional Appropriation to Professional Engineering Services Contract between the City and CivilTech Engineering, Inc. for Spring Shadows (North) Drainage and Paving, WBS No.:  M-410005-0001-3.

 

RECOMMENDATION:  (Summary)  Approve an ordinance appropriating additional funds to the Professional Engineering Services Contract with CivilTech Engineering, Inc. 

 

PROJECT NOTICE/JUSTIFICATION:  This project is part of the Capital Improvement Plan (CIP) and is required to address and reduce the risk of structural flooding.  Improvements include modification of street conveyance and sheet flow and provide detention, as needed, for mitigation.

 

DESCRIPTION/SCOPE:  This project provides for the design of storm drainage improvements, necessary concrete paving, curbs, sidewalks, driveways, and underground utilities. The project will serve the Spring Shadows North area.

 

LOCATION: The project is generally bound by Kempwood Drive on the north, and HCFCD Buttermilk Creek on the south, Palo Pinto Drive on the east, and Gessner Drive on the west.  The project is located in Key Map grids 450N and 450P.

 

PREVIOUS HISTORY AND SCOPE:  City Council approved the original Contract on June 04, 2014, under Ordinance No. 2014-0551. The scope of services under the original Contract consisted of Phase I, II and III Basic and Additional Services. Under this contract, the consultant completed Phase I – Preliminary Design services.

 

SCOPE OF THIS SUPPLEMENT AND FEE:  The requested additional appropriation will accomplish the following tasks: Phase II – Final Design including Basic and Additional Services, and Phase III – Construction Phase Services. The total Basic Services appropriation is $706,679.00. The additional services include, tree protection plans, traffic control plans, traffic signals, street lights, storm water pollution prevention plan, public meetings, independent quantity take off, TDLR plan review and reproduction services. The total Additional Services Fee under the additional appropriation is $446,944.00.

 

The total requested appropriation is $1,339,000.00 to be appropriated as follows: $1,153,623.00 for contract services and $185,377.00 for CIP Cost Recovery.

 

PAY OR PLAY PROGRAM:  The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Consultant provides health benefits to eligible employees in compliance with City policy.

 

M/WBE INFORMATION:  The M/WBE goal established for this project is 24%. The original Contract amount totals $759,500.00. The consultant has been paid $636,150.20 (83.76%) to date. Of this amount, $129,686.65 (20.39%) has been paid to M/WBE sub-consultants to date. Assuming approval of the requested additional appropriation, the contract amount will increase to $1,913,123.00. The Consultant proposes the following plan to meet the M/WBE goal:

 

Name of Firms

Work Description

Amount

% of Total Contract

 

Paid Prior M/WBE Commitment

-

$129,686.65

6.78%

Unpaid Prior M/WBE Commitment

-

$ 94,554.35

4.94%

1. Accessibility Check

TAS Review and Inspection

$ 790.00

0.04%

2. Atlas Civil Engineering PLLC

Engineering Services

$ 9,432.00

0.49%

3. B & E Reprographics, Inc.

Reproduction Services

$15,000.00

0.78%

4. Chief Solutions, Inc.

CCTV of existing storm sewer

$10,117.00

0.53%

5. Gunda Corporation, LLC

Traffic Control Plans

$85,615.00

4.48%

6. Kuo & Associates, Inc.

Engineering Services

$180,875.00

9.45%

 

 

Total

 

$526,070.00

 

27.49%

 

 

 

 

ESTIMATED FISCAL OPERATING IMPACT

 

PROJECT WBS#

FY17

FY18

FY19

FY20

FY21

FY17-FY21 Total

M-410005-0001-3

$0

$0

$0

$0

$0

$0

 

No significant Fiscal Operating impact is anticipated as a result of this project. 

 

 

_________________________________

Dale A. Rudick, P.E. Director

Department of Public Works and Engineering

Prior Council Action:
Ordinance 2014-0551, dated 06/04/2014
Amount of Funding:

$1,339,000.00 from Street & Traffic Control and Storm Drainage DDSRF

 

Fund 4042.

 

Original (previous) appropriation of $873,500.00 from Fund 4042 - Street & Traffic Control and Storm Drainage DDSRF.
Contact Information:

Ravi Kaleyatodi, P.E., CPM

Phone: (832) 395-2326

Senior Assistant Director