20YWF84 - Contract Award for Waterline Wrap Repairs

Agenda Item#: 32.


 
                               
Summary:

ORDINANCE awarding contract to REYTEC CONSTRUCTION RESOURCES, INC for Waterline Wrap Repairs; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for engineering and testing services and contingencies relating to construction of facilities financed by the Water & Sewer System Operating Fund

Background:

RECOMMENDATION:  (Summary)

Reject low bid, return bid bond, award construction contract to second low bidder and appropriate the necessary funds.

 

PROJECT NOTICE/JUSTIFICATION: This project will provide a work order based contract to repair water lines up to 16-inches in diameter in the distribution system on an emergency basis throughout the City.

 

DESCRIPTION/SCOPE: Work shall include the improvement and/or new installation of main water lines and service lines.  The main lines range in diameter up to 16-inches and the water service lines range in size from ¾-inch to 2-inches in diameter.  The contract duration for this project is 365 calendar days.  This is a work order based contract with work orders assigned on an as-needed basis.

 

LOCATION:  The project area is generally bounded by the City Limits.

 

BIDS:  Bids were received on September 29, 2016.  The six (6) bids are as follows:

 

                   Bidder                                                     Bid Amount

 

1.  Grava, LLC                                             $1,779,973.76 (Reject, Failed to use Addendum No.1)

2.  Reytec Construction Resources, Inc.        $1,940,052.55

3.  T Construction, LLC                                 $2,097,771.34

4.  Nerie Construction, LLC                           $2,115,295.65

5.  Middle East Engineering, LLC                   $2,133,417.00

6.  D. L. Elliott Enterprises, Inc.                     $2,273,014.44 

 

 

AWARD:

 

The apparent low bidder, Grava, LLC, with a bid of $1,779,973.76, failed to bid on the bid form included in Addendum No. 1.   All bidders submitted bid forms stating that all Addenda have been received, modifications to Bid Documents have been considered and all related costs are included in the Total Bid Price.  The apparent low bidder Grava, LLC, did not consider modifications to the bid form as stated in Document 00410A, Bid Form Part A.  Therefore, it is recommended that the bid be rejected and this construction contract be awarded to Reytec Construction Resources, Inc., with a low bid of $1,940,052.55.

 

PROJECT COST:      The total cost of this project is $2,097,055.18 to be appropriated as follows:

 

                                                               FY 17                              FY 18                          Total

 

Bid Amount                                      $1,125,230.48                  $814,822.07             $1,940,052.55

Contingencies                                       $56,261.53                    $40,741.10                  $97,002.63

Engineering and Testing Service          $34,800.00                    $25,200.00                  $60,000.00

Subtotal                                            $1,216,292.01                 $880,763.17             $2,097,055.18

 

Engineering and Testing Services will be provided by Gorrondona & Associates, Inc. under a previously approved contract.

 

HIRE HOUSTON FIRST:  The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston businesses and supports job creation.  In this case, Reytec Construction Resources, Inc. is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors.  In this case the contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION:  The low bidder has submitted the following proposed M/WBE participation to satisfy the 12.00% MBE goal, and 8.00% WBE goal for this project.

 

MBE-Name of Firm                                  Work Description             Amount        % of Contract

 

Castec Construction LLC                 Valves, Fire Hydrant and                

                                                         Concrete Replacement          $58,201.57        3.00%  

Reyes Pineda Construction Inc.       Valves, Fire Hydrant and

                                                          Concrete Replacement       $174,604.73        9.00%

 

                                                              MBE TOTAL                   $232,806.30      12.00%

 

WBE-Name of Firm                              Work Description                 Amount      % of Contract

 

Access Data Supply                        Concrete Ready Mix and  

                                                         Plumbing Materials               $155,204.20         8.00%

 

                                                              WBE TOTAL                   $155,204.20         8.00%

 

 

No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

 

                                                                          

Dale A. Rudick, P.E., Director

Department of Public Works and Engineering

 

 

 

 

 

Amount of Funding:

$2,097,055.18

Water and Sewer System Operating Fund No. 8300.

Contact Information:

Yvonne Forrest

Senior Assistant Director, Drinking Water Operations

Public Utilities Division

Phone: (832) 395-2847