CITY OF HOUSTON - CITY COUNCIL Meeting Date: 11/30/2016 District B, District H
Item Creation Date: 10/26/2016
20MAC85- Contract Award / Main Lane Industries, Ltd
Agenda Item#: 43.
| |
|
| | | | | | | | Summary:
ORDINANCE de-appropriating $7,690,771.00 out of METRO Projects Construction DDSRF, $1,096,362.00 out of Water & Sewer System Consolidated Construction Fund, and $1,951,867.00 out of Street & Traffic Control and Storm Drainage DDSRF, which was appropriated under ordinance 2015-0641, and appropriating $6,651,751.00 out of METRO Projects Construction DDSRF, $1,398,917.00 out of Water & Sewer System Consolidated Construction Fund, and $1,984,332.00 out of Street & Traffic Control and Storm Drainage DDSRF, awarding Contract to MAIN LANE INDUSTRIES, LTD. for Clinton Drive Paving and Drainage from Hirsch to Harvey Wilson Drive; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for engineering, testing, CIP Cost Recovery, design services during construction, and contingencies relating to construction of facilities financed by the METRO Projects Construction DDSRF, the Water & Sewer System Consolidated Construction Fund, and the Street & Traffic Control and Storm Drainage DDSRF - DISTRICTS B - DAVIS and H - CISNEROS |
| | | | | | | | Background:
SUBJECT: Contract Award for Clinton Drive Paving and Drainage from Hirsch to Harvey Wilson Drive. WBS Nos. N-000804-0001-3, N-000804-00R3-4, R-000500-0180-4, and S-000500-0180-4.
RECOMMENDATION: (Summary) De-appropriate funds from the previous contract; accept low bid, award construction Contract and appropriate funds.
PROJECT NOTICE/JUSTIFICATION: This project is part of the Street & Traffic Capital Improvement Plan (CIP) and is necessary to improve traffic flow/circulation, mobility, and drainage in the service area.
PREVIOUS HISTORY: This project was approved on June 11, 2014 by Ordinance 2014-0600 and on June 24, 2015 by Ordinance No. 2015-0641. Both contracts were terminated due to unforeseen underground private utility conflicts.
DESCRIPTION/SCOPE: This award consists of the design and construction of approximately 4,000 linear feet of resurfaced roadway and 5,400 linear feet of reconstructed roadways with curbs, replacement of the water and sanitary sewer lines, sidewalks, street lighting and improved local street drainage on Clinton Drive from Hirsch to Harvey Wilson Drive. The Contract duration for this project is 450 calendar days. This project was designed by TranSystems Consulting Corporation.
LOCATION: The project area is generally bound by I-10 East Freeway on the north, Buffalo Bayou on the south, Lathrop Street on the east and Hirsch Road on the west. The project is located in Key Map Grids 494K, L, & M.
BIDS: This project was advertised for bidding on March 18, 2016. Bids were received on May 12, 2016. The six (6) bids are as follows:
Bidder Bid Amount
|
1.
|
Main Lane Industries, Ltd.
|
$ 9,088,348.60
|
|
2.
|
ISI Contracting, Inc.
|
$ 9,152,899.95
|
|
3.
|
JFT Construction, Inc.
|
$ 9,851,613.15
|
|
4.
|
Total Contracting, Limited
|
$10,000,470.75
|
|
5.
|
Triple B Services, L.L.P.
|
$10,126,466.95
|
|
6.
|
SER Construction Partners, Inc.
|
$10,797,809.80
|
AWARD: It is recommended that this construction contract be awarded to Main Lane Industries, Ltd. with a low bid of $9,088,348.60 and that Addenda Numbers 1 and 2 be made a part of this Contract.
PROJECT COST: The total cost of this project is $10,035,000.00 to be appropriated as follows:
| · Bid Amount |
$9,088,348.60 |
| · Contingencies |
$ 454,500.00 |
| · Engineering and Testing Services |
$ 60,000.00 |
| · CIP Cost Recovery |
$ 363,988.79 |
| · Design Services During Construction |
$ 68,162.61 |
Engineering and Testing Services will be provided by Raba-Kistner Consultants, Inc. under a previously approved contract.
Design Services during Construction will be provided by TranSystems Consulting Corporation under a previously approved contract.
Construction Management Services will be provided by United Engineers, Inc. under a previously approved contract.
HIRE HOUSTON FIRST:
The proposed contract requires compliance with the City’s ‘Hire Houston First’ ordinance that promotes economic opportunity for Houston business and supports job creation. In this case Main Lane Industries, Ltd. is a designated HHF company, but they were the successful awardee without application of the HHF preference.
PAY OR PLAY PROGRAM:
The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.
M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 11% MBE goal and 7% WBE goal for this project.
|
MBE - Name of Fir
|
Work Description
|
Amount
|
% of Contract
|
|
1. Alamo Ready Mix, LLC
|
Ready-mix concrete manufacturing and distribution
|
$1,176,032.30
|
12.94%
|
|
|
TOTAL
|
$1,176,032.30
|
12.94%
|
|
WBE - Name of Firms
|
Work Description
|
Amount
|
% of Contract
|
|
1. Access Data Supply, Inc.
|
Concrete building products
|
$ 272,650.45
|
3.00%
|
|
2. KMA Contractors Services Inc.
|
Construction management and photos
|
$ 156,319.59
|
1.72%
|
|
|
TOTAL
|
$ 428,970.04
|
4.72%
|
|
SBE - Name of Firms
|
Work Description
|
Amount
|
% of Contract
|
|
1. Reliable Signal & Lighting
Solutions, LLC
|
Traffic signal installation
|
$ 363,533.94
|
4.00%
|
|
|
TOTAL
|
$ 363,533.94
|
4.00%
|
ESTIMATED FISCAL OPERATING IMPACT:
No significant Fiscal Operating impact is anticipated as a result of this project.
All known rights-of-way, easements and/or right-of-entry required for the project have been acquired. All known third party private utility relocations have been relocated.
_________________________________
Dale A. Rudick, P.E., Director
Department of Public Works and Engineering
|
| | | | | | | | Prior Council Action:
Ordinance No. 2015-0641, Date 6-24-2015
Ordinance No. 2014-0600, Date 6-11-2014 |
| | | | | | | | Amount of Funding:
$10,035,000.00 Total Cost
Appropriations
$6,651,751.00 from Fund No. 4040 - METRO Projects Construction DDSRF
$1,984,332.00 from Fund No. 4042 - Street & Traffic Control and Storm Drainage DDSRF
$1,398,917.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund
De-Appropriations
$7,690,771.00 Fund No. 4040 - METRO Projects Construction DDSRF
$1,951,867.00 Fund No. 4042 - Street & Traffic Control and Storm Drainage DDSRF
$1,096,362.00 Fund No. 8500 - Water and Sewer System Consolidated Construction Fund |
| | | | | | | | Contact Information:
Ravi Kaleyatodi, P.E., CPM
Phone: (832) 395-2326
Senior Assistant Director, Engineering Branch |
|