Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 11/15/2016
District C
Item Creation Date: 10/26/2016

20MAC86 Addtn'l Approp / Nathelyne A. Kennedy and Associates, L.P.

Agenda Item#: 45.


 
                               
Summary:

ORDINANCE appropriating $221,800.00 out of Metro Projects Construction DDSRF as an additional appropriation to Professional Engineering Services Contract between the City of Houston and NATHELYNE A. KENNEDY, L.P. for Shepherd and Durham Paving and Drainage from Washington to Dickson Street (Approved by Ordinance No. 2014-0298); providing funding for CIP Cost Recovery relating to construction of facilities financed by the Metro Projects Construction DDSRF - DISTRICT C - COHEN

Background:

SUBJECT:   Additional Appropriation to Professional Engineering Services Contract between the City and Nathelyne A. Kennedy and Associates, L.P. for Shepherd and Durham Paving and Drainage from Washington to Dickson Street.   WBS No. N-100003-0001-3. 

 

RECOMMENDATION:  (Summary) Approve an ordinance appropriating additional funds to the Professional Engineering Services Contract with Nathelyne A. Kennedy and Associates, L.P.  

 

PROJECT NOTICE/JUSTIFICATION:  This project is part of the Street and Traffic Capital Improvement Plan (CIP) and is necessary to meet City of Houston standards as well as improve traffic circulation, mobility and drainage in the service area.

 

DESCRIPTION/SCOPE:  This project consists of the design of approximately 4,000 linear feet of concrete roadways on Shepherd and Durham, modifying the existing roadway per Major Thoroughfare Freeway Plan (MTFP) standards plus a designated on-street bike lane per new Houston Bikeway Program.  The proposed project improvements include an underground drainage system to mitigate street flooding, new curbs, inlets, sidewalks, streetlights, signals and necessary underground utilities.

 

LOCATIONThe project area is generally bound by IH-10 on the north, Memorial Drive on the south, Westcott Street on the east and Yale Street on the west.  The project is located in Key Map Grids 492G, H, L, & M.

 

PREVIOUS HISTORY AND SCOPEThe original contract was approved on April 9, 2014 under Ordinance No. 2014-0298.  The scope of services under the original Contract consisted of Phase I Preliminary Design, Phase II – Final Design, Phase III –Construction Phase Services, and Additional Services.  Under this contract, the consultant completed Phase I – Preliminary Engineering Design. 

 

SCOPE OF THIS ADDITIONAL APPROPRIATION AND FEE:  The requested additional appropriation will accomplish the following tasks:  Phase II – Final Design and Phase III Construction Phase Services for reconfiguration of the existing four-lane roadway plus a bike lane and connecting side streets, which were not included in the original scope.  $92,700.00 are budgeted as Basic Services Fee computed by lump sum.  Certain other Additional Services are proposed to be paid on a reimbursable basis.  Additional Services are currently anticipated to include televising sewer line, tree protection plan, boundary survey, and topographic survey which comprise the bulk of the funds.  The total Additional Services Fee under the additional appropriation is $96,865.00. 

 

The total requested appropriation is $221,800.00 to be appropriated as follows: $189,565.00 for contract services and $32,235.00 for CIP Cost Recovery.

 

PAY OR PLAY PROGRAMThe proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Consultant provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION:  The M/WBE goal established for this project is 24%.  The original Contract amount totals $972,436.00.  The consultant has been paid $293,997.08 (30.23%) to date.  Of this amount, $115,225.80 (39.19%) has been paid to M/WBE sub-consultants to date.  Assuming approval of the requested additional appropriation, the contract amount will increase to $1,162,001.00.  The Consultant proposes the following plan to meet the M/WBE goal.

 

Name of Firms

Work Description

       Amount

% of Total Contract

Paid Prior M/WBE Commitment

 

$115,225.80

9.91%

Unpaid Prior M/WBE Commitment

 

$191,355.20

16.47%

Kuo & Associates, Inc.

Topographic boundary Surveying, ROW Survey Corner Clips

$ 72,350.00

6.23%

Chief Solutions, Inc.

Televising Sanitary Lines

$ 15,000.00

__________

1.29%

______

 

Total

$393,931.00

33.90%

 

 

ESTIMATED FISCAL OPERATING IMPACT

 

PROJECT WBS#

FY17

FY18

FY19

FY20

FY21

FY17-FY21 Total

N-100003-0001-3

$0

$0

$0

$0

$0

$0

 

 

No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

_________________________________

Dale A. Rudick, P.E. Director

Department of Public Works and Engineering

Prior Council Action:
Ordinance #  2014-0298    04/09/2014
Amount of Funding:

$221,800.00 from Fund No. 4040 - METRO Projects Construction DDSRF

   

Original (previous) appropriation of $1,118,300.00 from Fund No. 4040 - METRO Projects Construction DDSRF                        
Contact Information:

Ravi Kaleyatodi, P.E., CPM

Phone: (832) 395-2326

Senior Assistant Director, Engineering Branch

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material