Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 11/9/2016
ALL
Item Creation Date: 10/20/2016

20JAI648 Contract Award/rePipe Construction

Agenda Item#: 44.


 
                               
Summary:

ORDINANCE appropriating $697,390.00 out of Water & Sewer System Consolidated Construction Fund; awarding contract to REPIPE CONSTRUCTION, LLC dba IPR SOUTH CENTRAL, LLC for Wastewater Collection System Rehabilitation and Renewal (Force Main); setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for engineering and testing, and contingencies relating to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund - (WW 4235-87)

Background:

SUBJECTContract Award for Wastewater Collection System Rehabilitation and Renewal (Force Main), WBS# R-000035-0018-4.

 

RECOMMENDATION:  (Summary)  Accept low bid, award construction contract, and appropriate funds.

 

SPECIFIC EXPLANATION: This project is part of the Neighborhood Sewer Rehabilitation Program and is required to renew/replace various deteriorated neighborhood collection systems throughout the City. The project involves sanitary sewer rehabilitation by point repair method. The purpose is to reduce sanitary sewer overflows, which is accomplished by renewal/rehabilitation of deteriorated collection systems.

 

DESCRIPTION/SCOPE: This project consists of sanitary sewer rehabilitation by point repair method. The contract duration for this project is 730 calendar days. 

 

LOCATION:  The work order project area is generally bounded by the City Limits.

 

BIDS:  Five (5) bids were received on August 04, 2016 for this project as follows:

 

 

Bidder

Bid Amount

1.

rePipe Construction, LLC dba IPR South Central, LLC

$640,371.42

2.

Grava LLC

$645.356.60

3.

Texas Pride Utilities, LLC

$655,356.60

4.

T Construction, LLC

$664,287.76

5.

Nerie Construction, LLC

$754,198.81

 

AWARD: It is recommended that this construction contract be awarded to rePipe Construction, LLC dba IPR South Central, LLC, with a low bid of $640,371.42.

 

PROJECT COST:  The total cost of this project is $697,390.00 to be appropriated as follows:

 

·

Bid Amount

$640,371.42

·

Contingencies

$32,018.58

·

Engineering Testing Services

$25,000.00

 

Engineering Testing Services will be provided by Geotest Engineering, Inc., under a previously approved contract.

 

HIRE HOUSTON FIRST: Hire Houston First does not apply to this expenditure, because it involves the use of federal funds and is subject to specific procurement rules of the federal government.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s Pay or Play ordinance regarding health benefits for employees of City contractors. In this case, the contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 12.94% MBE goal, and 8.72% WBE goal for this project.

 

MBE – Name of Firms

Work Description

Amount

% of Contract

Chief Solutions, Inc.

Clean & Televise Sewer Line

$22,413.00

3.50%

5M Rope & Supply, LLC

Supplies

$9,221.35

1.44%

J.A. Gamez Trucking Services

Dump Trucking Services

$6,403.71

1.00%

MMG Contractors

Open Cut/Point Repairs

$44,826.00

7.00%

 

MBE TOTAL

$82,864.06

12.94%

 

 

 

 

WBE – Name of Firms

Work Description

Amount

% of Contract

Deanie Hayes, Inc.

Supplies

$14,856.62

2.32%

Advantage Manhole & Concrete Services, Inc.

Manhole Rehabilitation

$40,983.77

6.40%

 

WBE TOTAL

$55,840.39

8.72%

 

ESTIMATED FISCAL OPERATING IMPACT:

 

PROJECT WBS#

FY17

FY18

FY19

FY20

FY21

FY17-FY21 Total

R-000035-0018-4

$0.00

$0.00

$0.00

$0.00

$0.00

$0.00

 

No significant Fiscal Operating impact is anticipated as a result of this project.

 

All known rights-of-way and easements required for this project have been acquired.

 

Amount of Funding:
$697,390.00 from Water and Sewer System Consolidated Construction Fund No. 8500. This project is eligible for low interest funding through a State Revolving Fund (SRF) Equivalency loan.   
Contact Information:

Jason Iken, P.E.

Senior Assistant Director

Phone:  (832) 395-4989
ATTACHMENTS:
DescriptionType
Signed RCASigned Cover sheet
MapBackup Material