Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/7/2016
District J
Item Creation Date:

25PARK285 - Burnett Bayland Skatepark - P^2MG, LLC dba P2MG, LLC - F-000803-0001-4

Agenda Item#: 17.


 
                               
Summary:

ORDINANCE appropriating $347,000.00 out of Parks Consolidated Construction Fund, $200,000.00 out of Parks & Recreation Dedication Fund, $114,500.00 out of Reimbursement of Equipment/Projects Fund, and $277,696.00 out of the Contributed Capital Projects Fund; awarding construction contract to P^2MG, LLC DBA P2MG, LLC for Burnett Bayland Skatepark; setting a deadline for the proposer's execution of the contract and delivery of all bonds, insurance and other required contract documents to the City; holding the proposer in default if it fails to meet the deadlines; providing funding for engineering and materials testing services, and contingencies relating to construction of facilities financed by Parks Consolidated Construction Fund, the Parks & Recreation Dedication Fund, Reimbursement of Equipment/Projects Fund, Contributed Capital Projects Fund, and the Tony Hawk Grant Fund - DISTRICT J - LASTER

Background:

SPECIFIC EXPLANATION:     The General Services Department (GSD) recommends that City Council award a                  construction contract to P^2MG, LLC dba P2MG, LLC (P2MG) on the proposal amount of $876,000.00 to provide construction services for Burnett Bayland Skatepark for the Houston Parks and Recreation Department.  The Council District J Service Fund and Neighborhood Centers, Inc. will reimburse the Reimbursement of Equipment/Projects Fund.

PROJECT LOCATION:  6000 Chimney Rock (Key Map No. 531Q)                                                                                                                   

PROJECT DESCRIPTION: This project will construct a new 17,500 square foot skatepark. The skatepark includes an entry plaza, walks and skate park with various features or tricks.  The features include a volcano, bowl, upper decks, grind ledges, stairs and handrails, flat bars, various bank types, a quarter pipe and multiple steel pipes.  The project will also include re-routing a portion of the existing trail, new electrical service, lighting, site grading, drainage and detention.

The contract duration for this project is 180 calendar days.  Clark Condon Associates, Inc. is the design consultant for the project. 

PROPOSALS:  On January 29 and February 5, 2016, GSD advertised a Request for Competitive Sealed Proposals (CSP) for construction services for the Burnett Bayland Skatepark.  The CSP contained selection criteria that ranked respondents on experience, general contractor and skatepark sub-contractor team members, and contractor responsibility. The Statements of Qualifications were due on February 18, 2016 and four firms responded.  GSD evaluated the respondents and three of the four firms received sufficient points and were requested to submit proposals. Two of the three selected firms submitted proposals. P^2MG submitted the lowest proposal and offers the best value for the City based on the advertised criteria.

The two proposers are ranked as follows:

 

Proposer:

1.            P^2MG, LLC dba P2MG, LLC

2.       Millis Development and Construction, Inc.

AWARD: It is recommended that City Council award the construction contract to P^2MG and appropriate funds for the project, including an additional appropriation of $29,396.00 for engineering and materials testing services to All-Terra Engineering, Inc.

FUNDING SUMMARY:   

$

876,000.00

Construction Contract Services

$

43,800.00

5% Contingency

$

919,800.00

Total Contract Services

$

29,396.00

Engineering and Materials Testing

$

949,196.00

Total Funding

   

   PAY OR PLAY PROGRAM:  The proposed contract requires compliance with the City’s “Pay or Play” Ordinance regarding health benefits for employees of City contractors.  In this case, the contractor provides benefits to eligible employees in compliance with City policy.

 

   HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s “Hire Houston First” (HHF) Ordinance that promotes economic opportunity for Houston businesses and supports job creation. In this case, P^2MG is a designated HHF company, but they were the successful awardee without application of the HHF preference. 

 

CIP FISCAL NOTE: The five-year projected operational and maintenance costs for this project are noted below:

      

       Capital Project Information

          See attached Form A for a breakdown of capital costs.   

 

Estimated Fiscal Operating Impact

 

 

 

 

 

 

 

Project

FY17

FY18

FY19

FY20

FY21

FY17-21

Burnett Bayland Skatepark

WBS# F-000803-0001-4

$12,000

$50,000

$52,000

$54,000

$56,000

$224,000

 

 

 

 

 

Amount of Funding:

$      347,000.00  Parks Consolidated Construction Fund (4502)

$      200,000.00  Parks & Recreation Dedication Fund (4035)

$      114,500.00  Reimbursement of Equipment/Projects Fund (1850)

$      277,696.00  Contributed Capital Projects Fund (4515)

$        10,000.00  Tony Hawk Grant Fund (5040)

$      949,196.00  Total Funding
Contact Information:
Jacquelyn L. Nisby                 Phone:  832-393-8023