Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 6/21/2016
District A, District B, District C, District D, District E, District F, District G, District H, District I, District J, District K
Item Creation Date: 6/2/2016

20JAI635 Accept Work/Sewer and Storm Maintenance

Agenda Item#: 10.


 
                               
Summary:

RECOMMENDATION from Director Department of Public Works & Engineering for approval of final contract amount of $537,221.01 and acceptance of work on contract with SEWER AND STORM MAINTENANCE, LLC for Sanitary Sewer Cleaning and Television Inspection In Support of Rehabilitation - 0.52% over the original contract amount and under 5% contingency (4277-58)

Background:

SUBJECTAccept Work for Sanitary Sewer Cleaning and Television Inspection In Support of Rehabilitation, WBS# R-000266-0181-4.

 

RECOMMENDATION:  (Summary)  Pass a motion to approve the final contract amount of $537,221.01, which is 0.52% over the original contract amount and under the 5% contingency amount, accept the work, and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: Under this project, the contractor provided sanitary sewer cleaning and television inspection in support of rehabilitation to deteriorated sewer collection systems throughout the City.

 

DESCRIPTION/SCOPE: This project consisted of sanitary sewer cleaning and television inspection in support of rehabilitation. The project was awarded to Sewer and Storm Maintenance, LLC with an original contract amount of $534,446.25. The Notice to Proceed date was 06/14/2012 and the project had 730 calendar days for completion.

 

LOCATION:  This work order project was located at various locations within Council Districts A, B, C, D, E, F, G, H, I, J and K.

 

CONTRACT COMPLETION AND COST:  The contractor, Sewer and Storm Maintenance, LLC, has completed the work under the contract.  The contract was completed within the contract time with an additional 120 days approved by Change Order No.1. The final cost of the project is $537,221.01, an increase of $2,774.76 or 0.52% over the original contract amount. More cleaning and television inspection were needed than anticipated.

 

The final amount of this work order contract was not affected by Change Order No. 1.

 

MWDBE PARTICIPATIONNo City M/WBE participation goal was established for this project as the contract amount did not exceed the threshold of $1,000,000.00 required for a goal oriented contract per Section 15-82 of the Code of Ordinances.

Prior Council Action:
Ordinance 2012-0116, dated 02/08/2012
Amount of Funding:

No additional funding required.

 

Original appropriation of $566,169.00 for construction and contingencies from Water and Sewer System Consolidated Construction Fund No. 8500.
Contact Information:

Jason Iken, P.E.

Senior Assistant Director

Phone:  (832) 395-4989