CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 6/21/2016
District A
Item Creation Date: 5/27/2016

20BB179 Contract Award/SER

Agenda Item#: 55.


 
                               
Summary:

ORDINANCE appropriating $3,392,000.00 out of Water & Sewer System Consolidated Construction Fund and $11,938,000.00 from Street & Traffic Control and Storm Drainage DDSRF, awarding contract to SER CONSTRUCTION PARTNERS, LLC. for Neighborhood Street Reconstruction Project 456; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for engineering, testing, CIP Cost Recovery, construction management and contingencies relating to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund and Street & Traffic Control and Storm Drainage DDSRF - DISTRICT A - STARDIG

Background:

SUBJECT:  Contract Award for Neighborhood Street Reconstruction (NSR) Project 456. WBS No. N-000388-0001-4, R-000500-0158-4 and   S-000500-0158-4.

 

RECOMMENDATION:  Accept low bid, award construction Contract and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION:  This project is part of the Capital Improvement Plan which replaces existing residential streets that have been deteriorated beyond economical repair and normal maintenance, and improves drainage.

 

DESCRIPTION/SCOPE:  This project consists of neighborhood street reconstruction.  The proposed improvements will consist of concrete roadways with curbs, sidewalks and underground utilities, as required.

 

The Contract duration for this project is 660 calendar days.  This project was designed by Bury, Inc.

 

LOCATION:  This project is generally bounded by Hammerly on the north, Brittmore Road to the east, IH-10 westbound frontage road to the south and Addicks Dam Road on the west.  The project is located in Key Map Grids 449T, 449U, 449X, 449Y, and 489B.

 

BIDS:  This project was advertised for bidding on March 25, 2016.  Bids were received on April 28, 2016.  The eleven bids are as follows:

                        Bidder                                                                 Bid Amount

1.      SER Construction Partners, LLC                        $12,742,572.02

2.      Reytec Construction Resources, Inc.                  $13,292,972.00

3.      Triple B Services, LLP                                         $13,455,272.00

4.      JFT Construction, Inc.                                         $13,557,268.05

5.      Joslin Construction Texas, LLC                           $13,817,565.00

6.      Resicom, Inc.                                                       $13,902,996.37

7.      CYMI Industrial, Inc.                                            $13,946,116.50

8.      Total Contracting Limited                                     $14,105,492.00

9.      ISI Contracting, Inc.                                             $14,135,568.64

10.   Main Lane Industries, Ltd.                                    $14,184,539.50

                   11.   Conrad Construction Co., Ltd.                              $15,475,381.09

 

AWARD:  It is recommended that this construction contract be awarded to SER Construction Partners, LLC. with a low bid of $12,742,572.02 and that Addendum Number 1, Addendum No. 2, and Addendum Number 3 be made a part of this Contract.

 

PROJECT COST:  The total cost of this project is $15,330,000.00 to be appropriated as follows:

 

·                  Bid Amount                                               $12,742,572.02

·                  Contingencies                                           $     637,128.60

·                  Engineering and Testing Services            $     350,000.00

·                  Construction Management                        $     960,000.00

·                  CIP Cost Recovery                                   $     640,299.38

 

Engineering and Testing Services will be provided by Terracon Consultants, Inc. under a previously approved contract.  Construction Management Services will be provided by IDCUS, Inc. dba IDC, Inc. under a previously approved contract.

 

HIRE HOUSTON FIRST:  The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation.  In this case, SER Construction Partners, LLC is a designated HHF company, but they were successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM:  The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors.  In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WSBE PARTICIPATION:  The contractor has submitted the following proposed plan to satisfy the 11% MBE goal and 7% WBE goal:

 

      MBE - Name of Firm Work Description Amount % of Total Contract
1. Bedo Construction Products, Inc.    Supplier of Precast Concrete Products $350,000.00  2.75%
2. PRV Services, Inc. Roadway Paving $550,000.00 4.32%
3. C&C Traffic Control, LLC Flagging Services $350,000.00 2.75%
4. Reliable Signal & Lighting Solutions, LLC Conduit Installation $160,000.00 1.26%
    TOTAL MBE    $1,410,000.00 11.08%
         
  WBE - Name of Firm Work Description Amount % of Total Contract
1. H&E Aggregate, LLC Supplier of Aggregate Products $482,000.00 3.78%
    TOTAL WBE    $482,000.00 3.78%
         
  SBE - Name of Firm Work Description Amount % of Total Contract
1. Technical Assurance, LLC Bonding Agrent $130,000.00 1.02%
2. Semarck Landscape Services, Inc. Landscape Contractor $280,000.00 2.20%
    TOTAL SBE    $410,000.00 3.22%

 

All known rights-of-way, and easements have been acquired.  Driveway rights-of-entry are in the process of being acquired.

 

All known third party utilities have been relocated.

 

Amount of Funding:

$15,330,000.00 Total Cost

 

$  3,392,000.00 from Water and Sewer System Consolidated Construction Fund No. 8500

 

$11,938,000.00 from Fund No. 4042 – Street & Traffic Control and Storm Drainage DDSRF
Contact Information:

Ravi Kaleyatodi, P.E., CPM

Phone:  (832) 395-2326

Senior Assistant Director
ATTACHMENTS:
DescriptionType
Signed RCASigned Cover sheet
MapsBackup Material