Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 6/14/2016
District B, District C, District D, District H
Item Creation Date: 5/25/2016

20PJ65 Accept Work/Durwood Greene

Agenda Item#: 3.


 
                               
Summary:

RECOMMENDATION from Director Department of Public Works & Engineering for approval of final contract amount of $5,556,787.52 and acceptance of work on contract with DURWOOD GREENE CONSTRUCTION CO. for City Wide Overlay Package #20 - 2.06% over the original contract amount and under 5% contingency amount - DISTRICTS B - DAVIS; C - COHEN; D - BOYKINS and H - CISNEROS

Background:

SUBJECT: Accept Work for City Wide Overlay Package #20; WBS No. N-321037-0069-4.  

 

RECOMMENDATION: (Summary) Pass a motion to approve the final Contract Amount of $5,556,787.52 or 2.06% over the original Contract Amount and under 5% contingency amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City Wide Overlay Program and was required to improve and maintain a safe road surface and accessibility

 

DESCRIPTION/SCOPE: The project consisted of the resurfacing of arterial and major thoroughfare streets with asphalt along with the repair and improvements to curbs and accessible ramps.  The project involved the design and construction of hot mix asphaltic concrete, base repair and pavement markings as needed.  The project was designed In-House with 365 calendar days allowed for construction.  The project was awarded Durwood Greene Construction Co. with an original Contract Amount of $5,444,850.00.

 

LOCATION:  The project areas are located in major thoroughfares and arterials throughout the City of Houston. 

 

Street
From To Key Map Council District
Colquitt Yupon Montrose 493S C
Dunlavy Westheimer Rd.    W. Alabama   492V C
Graustark     Alabama Richmond 493S C
Holcomb Blvd.    Edloe Main 532G, 532F, 532E   C
Laura Koppe Road   Dodson Hirsch 454F  H
Mesa Liberty Road N. Green 455Q, L&G B
Swingle Scott Cullen 573 Q&R D
White Oak Studewood Houston Ave   493A, 492B, 493C H

 

CONTRACT COMPLETION AND COST:  The Contractor, Durwood Greene Construction Co. has completed the work under the subject Contract. The project was completed on time with an additional 108 days approved by Change Order No. 1.  The final cost of the project, including overrun and underrun of estimated unit price quantities is $5,556,787.52, an increase of $111,937.52 or 2.06% over the original Contract Amount and under 5% contingency amount .

 

The increased cost is a result of the difference between planned and measured quantities. This increase is primarily the result of an overrun in various Base Unit Price Items and Extra Unit Price Items, which was necessary to complete the project.

 

M/W/SBE PARTICIPATION:  The M/W/SBE goal established for this project was 19%.  According to Office of Business Opportunity, the participation was 20.85%.  Contractor’s M/W/SBE performance evaluation was rated Outstanding.

 

 

Prior Council Action:
Ordinance 2014-0003, dated 01/08/2013
Amount of Funding:

No additional funding required.

 

Total (original) appropriation of $6,293,232.00 from Fund 4040 – METRO Projects Construction DDSRF. 
Contact Information:

Joseph T. Myers, P.E.

Senior Assistant Director

Phone: (832) 395-2355
ATTACHMENTS:
DescriptionType
Signed RCASigned Cover sheet
MapsBackup Material