SPECIFIC EXPLANATION: The General Services Department recommends that City Council award a construction contract to DNB Enterprises, Inc. on the low bid amount of $1,712,756.00 to provide construction services for Remediation and Tank Replacement at the Japhet Street fleet and fuel facility for the Public Works and Engineering Department.
PROJECT LOCATION: 100 Japhet Street, Houston, Texas (Key Map 484-L)
PROJECT DESCRIPTION: The scope of work consists of removing one 25,000 gallon gasoline underground storage tank (UST), two 25,000 gallon diesel USTs, with associated appurtenances. The work also includes the installation of four 25,000 gallon USTs and disposal of aqueous liquid, saw-cutting, demolition and removal of concrete paving over the USTs, backfilling and compaction, waste classification, loading, hauling and proper disposal.
The contract duration for this project is 180 calendar days.
BIDS: The project was advertised in accordance with the requirements of the State of Texas bid laws on March 11 and March 18, 2016. Five contractors attended the pre-bid meeting on March 22, 2016. The following two bids were received on March 31, 2016:
Bidder |
Bid Amount |
DNB Enterprises, Inc. |
$1,712,756.00* |
Cobb Environmental |
Non-responsive |
*GSD reviewed the bid amount and believes it is reasonable for the specified scope of work.