Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/15/2015
District B
Item Creation Date: 11/23/2015

HAS - Professional Services Contract with Fentress Architects, Ltd. for AE Design Services for IAH MLIT; Project 826

Agenda Item#: 45.


 
                               
Summary:

ORDINANCE appropriating $50,095,000 out of HAS Consolidated ITRP AMT Construction Fund and $674,239 out of Airports Improvement Fund and approving and authorizing Professional Services Contract between the City of Houston and FENTRESS ARCHITECTS, LTD. for Architectural and Engineering Design Services for the IAH Mickey Leland International Terminal (Project No. 826); providing funding for the Civic Art Program - DISTRICT B - DAVIS

Background:

SUBJECT: Professional Services Contract with Fentress Architects, Ltd. for Architect Engineer (AE) Design Services for the IAH Mickey Leland International Terminal (MLIT); Project No. 826 (WBS: A-000800-0008-3-01-01)  

 

RECOMMENDATION: Enact an ordinance to approve a contract for professional services with Fentress Architects, Ltd. for Architect Engineer (AE) Design Services for the IAH Mickey Leland International Terminal (MLIT) and appropriate the necessary funds to finance the cost of these services.

 

PROJECT LOCATION: George Bush Intercontinental Airport/Houston (IAH)

SPECIFIC EXPLANATION:
The Houston Airport System (HAS) has identified a significant need for the development of additional facilities at IAH to handle aircraft, passengers, and cargo departing to, and arriving from, domestic and international destinations on scheduled and chartered flights.

To support the airlines’ growth plans in Houston, the HAS and airlines will complete a major capital improvement program, known as the IAH Terminal Redevelopment Program (ITRP), that will include constructing a new 11-gate concourse on the north side of Terminal B, becoming the “New Terminal C North” and reconstructing and integrating the existing Terminal C North and Terminal D into a new single common-use international facility (the Mickey Leland International Terminal (MLIT)). The expansion of the terminal facilities will also necessitate an enlargement of certain components of the existing Federal Inspection Services (FIS) facility. The improvement plan will also include several enabling projects to serve the newly constructed facilities as well as a new roadway system, airfield improvements, and parking structure for increased parking capacity.

The MLIT Architect Engineer (AE) basic design services will include services for all disciplines required to complete the design of the MLIT and construction administration. Services will include, but not be limited to: Architectural Programming and Design, Interior Design, Structural Engineering, Blast Protection/Resistance, Conveying Systems, Plumbing Engineering, Fire Protection Systems Design, Mechanical Engineering, Building Automation and Control Systems, Electrical Engineering, Lighting Design, Technology Integration Services, Technology and Communications, Security Systems, Acoustical Design, Vibration Analysis, Civil Engineering, Specialty Services including Baggage Handling Systems, Pre-Conditioned Air Systems and other systems as described within the scope of services, Traffic Design, Building Information Modeling and Geographical Information Systems (BIM/GIS), Sustainability and Energy Efficiency Design, Visual Communications including Signage, Graphics and Wayfinding, Furniture, Fixtures and Equipment (FF&E), Life Safety Code Compliance, Commissioning Coordination, Operational Readiness, Activation and Transition (ORAT) Coordination, Construction Cost Estimating and other services as mutually agreed to by the AE and HAS, among other services.

A Request for Qualifications (RFQ) was advertised in accordance with City policy, and Statements of Qualification (SOQ) were received from nine (9) firms. The Evaluation Committee, comprised of HAS senior managers, evaluated and ranked the SOQs based on criteria contained in the RFQ. Three (3) firms were short-listed and interviewed by the Evaluation Committee and Fentress Architects, Ltd. was recommended for contract award. The selection process was observed by members of a Design Committee (comprised of representatives from the American Institute of Architects (AIA), the University of Houston School of Architecture, Rice University School of Architecture, and Prairie View A&M University School of Architecture), representatives of United Airlines and a representative of the IAH Foreign Flag carriers, and the ITRP Executive Program Manager.

In additional to the basic design services, the AE will coordinate the MLIT design and recommended phasing approach with other design teams, the City, airline representatives, project stakeholders and other tenants and contractors executing concurrent capital improvement and tenant improvement projects. These projects include the United Airlines’ New Terminal C North and the Landside Enabling Utilities project.

HAS may be requesting City Council’s approval of additional appropriations in support of ancillary construction administration services as the MLIT design and construction phasing becomes better defined. A portion of the spending under this contract may be eligible for reimbursement under either the FAA AIP or PFC programs.

Project Cost:
The total appropriation is as follows:

$ 50,095,000      Design Services
$       674,239     Civic Art
$ 50,769,239      TOTAL APPROPRIATION

Pay or Play: The proposed contract requires compliance with the City’s “Pay or Play” ordinance regarding health benefits for employees of City contractors. In this case, the contractor provides benefits for some employees but will pay into the Contractor Responsibility Fund for others, in compliance with City policy.

M/WBE Participation: The Minority/Women Business Enterprise (M/WBE) goal for this contract is 30%. Fentress Architects, Ltd. proposes 32.65% M/WBE participation through the services performed by the following firms:

 

Certified Firm                          Type of Work                                                %
STOA International                 Architects Architecture, BIM/GIS Design   9%
RdlR Architects                        Programming, Interior Architecture       2.5%
Smith & Company                     Interiors                                               1.25%
Huerta & Associates                   Architects Architectural Support         1.25%
Archi*Technics/3         Design Development, Construction Documents 1.25%
Bradlink                                    WMSBE Coordinator                               0.5%
Henderson & Rogers                 Structural Engineer                                3%
Jones Engineers                         Mechanical Engineer                           2.7%
Hunt & Hunt Engineering            Electrical Engineer                               2.7%
4b Technology                           Technology Communications               4.5%
PGA Engineers                           Security Systems                                 0.5%
Isani Consultants                             Civil Engineering                             1%
United Engineers                         Civil Engineering                                 1%
OMEGA Engineers                         Civil Engineering                               1%
Clark Condon                               Landscape Architect                            0.5%

 

The City Council Budget and Fiscal Affairs Committee was briefed on this contract on November 19, 2015.

Amount of Funding:
$50,095,000   HAS Consolidated ITRP AMT Construction Fund (8207)
$     674,239   HAS Aprt Improvement Fund (8011)
$50,769,239   TOTAL
Contact Information:
Kathy Elek               Phone: 281/233-1826
Robert Barker                      281/233-1953