SUBJECT: Accept Work for Sanitary Sewer Rehabilitation by Cured-In-Place Pipe Method (LDS), RePipe Construction, LLC, WBS# R-002013-0028-4.
RECOMMENDATION: (Summary) Pass a motion to approve the final contract amount of $2,424,121.03, which is 0.24% over the original contract amount and under the 5% contingency amount, accept the work, and authorize final payment.
PROJECT NOTICE/JUSTIFICATION: Under this project, the contractor provided sanitary sewer rehabilitation by cured-in-place pipe method to deteriorated sewer collection systems throughout the City.
DESCRIPTION/SCOPE: This project consisted of sanitary sewer rehabilitation by cured-in-place pipe method. The project was awarded to RePipe Construction, LLC with an original contract amount of $2,418,251.10. The Notice to Proceed date was 12/13/2011 and the project had 540 calendar days for completion.
LOCATION: The project was located at various locations within Council Districts B, H, and I.
CONTRACT COMPLETION AND COST: The contractor, RePipe Construction, LLC, has completed the work under the contract. The contract was completed within the contract time. The final cost of the project is $2,424,121.03, an increase of $5,869.93 or 0.24% over the original contract amount. More cured-in-place pipe was needed than anticipated.
The final amount of this work order contract was not affected by Change Orders No. 1, and No. 2.
MWDBE PARTICIPATION: The MWDBE goal for this project was 18%. According to the Office of Business Opportunity, the actual participation was 19.79%. The contractor was awarded a “Satisfactory” rating from the Office of Business Opportunity.