Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/9/2015
District B, District H
Item Creation Date: 8/5/2015

20EW003B Pass a motion approving Change Order No. 1 for the Northside Sewer Relief Tunnel Rehabilitation Area No. 4; Oscar Renda Contracting, Inc., WBS No. R-002003-0008-4.

Agenda Item#: 5.


 
                               
Summary:

RECOMMENDATION from Director Department of Public Works & Engineering for approval of Change Order No. 1 in the amount of $809,681.34 for the Northside Sewer Relief Tunnel Rehabilitation Area No. 4 on contract with OSCAR RENDA CONTRACTING, INC - DISTRICTS B - DAVIS and H - GONZALEZ

This item should only be considered after passage of Item 4 above

Background:

SUBJECT: Pass a motion approving Change Order No. 1 for the Northside Sewer Relief Tunnel Rehabilitation Area No. 4; Oscar Renda Contracting, Inc., WBS No. R-002003-0008-4.

 

RECOMMENDATION: (Summary) Adopt a motion approving Change Order No. 1 in the amount of $809,681.34 for the Northside Sewer Relief Tunnel Rehabilitation Area No. 1.  

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the City’s ongoing program for Northside Sewer Relief Tunnel Rehabilitation. It is required to rehabilitate Area No.4 of the tunnel, which has moderate to severe corrosion, and to protect it from future corrosion.

 

DESCRIPTION/SCOPE: The project consists of sliplining approximately 4,689 linear feet of 132-inch monolithically cast in place reinforced concrete sanitary sewer with 120-inch fiberglass reinforced polymer mortar pipe. CH2M Hill designed the project with 500 calendar days allowed for construction.  The project was awarded to Oscar Renda Contracting, Inc. with an original Contract Amount of $10,662,609.00 

 

LOCATION:  The project area is generally bound by IH-10 on the north, Buffalo Bayou on the south, Bayou Road on the east and Elysian St. on the west. The project is located in Key Map Grids 493M & 494J.

 

 

CHANGE ORDER No. 1: An approval is requested for Change Order No. 1 in the amount of $809,681.34  and 99 days of time extension for additional work required to install new tunnel access shaft, perform exploratory drilling to locate NSRT and establish alternate locations of three tunnel access shafts, delay cost compensation and additional silt and debris removal.  A portion of the existing NSRT follows S-curve alignment at 60 feet depth and is located in an easement. The location of the NSRT was not found as shown on the as-built drawings. This scope of work is necessary to complete the execution of this project.

 

The Change Order No. 1 will cover the additional work identified and leave the 5% contingencies balance for the completion of remaining contract work.  

 

MBE/SBE PARTICIPATION:  The MBE/SBE goal established for this project was 21%. According to Office of Business Opportunity the Contractor’s to date MBE/SBE performance is 3.24%. As noted in the original RCA, the largest portion of the MBE/SBE participation is going to be purchase and installation of pipe. Since that portion of the project has not been reached, there is minimal MBE/SBE utilization to report at this time.

Prior Council Action:
Ordinance #2012-0582, dated 06/20/2012
Amount of Funding:

No Additional funding required.

 

Previous (original appropriation) of $12,300,600.00 from Water and Sewer System Consolidated Construction Fund No. 8500.  Subsequent $809,681.34 from Water and Sewer System Consolidated Construction Fund No. 8500. 

Contact Information:

Joseph T. Myers, P.E.

Senior Assistant Director

Phone: (832) 395-2355