RECOMMENDATION:
Approve a resolution in support of applications to the Harris County Precinct 4 Places 4 People: 2025 Call for Projects; authorizing the Director of Houston Public Works or designee to act as a signatory on the applications with authority to apply.
SPECIFIC EXPLANATION:
Harris County Precinct 4 is seeking Capital Improvement Projects (CIP) and maintenance partnership projects from area agencies to serve communities throughout Harris County Precinct 4. This applies to funding for study, conceptual, and final design, right-of-way acquisition, and construction of capital and maintenance projects.
Houston Public Works (HPW) prepared two applications for funding partnership on the CIP projects listed below. If any projects are selected for partnership, HPW will coordinate with Harris County to develop an Interlocal Agreement (ILA) that defines project roles and responsibilities for City Council and Commissioner's Court approval. Matching funds will be identified and appropriated at that time.
Alief Forest South Area Drainage and Paving. This project provides for the design and construction of concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting and necessary underground utilities.
Lakeside Estates Dr. Street Rehabilitation. Concrete panel replacement and associated infrastructure (curbs, sidewalks, drainage inlets) of 1.4 miles at the intersection of Lakeside Estates Dr. and Lynbrook Dr.
The table below identifies funding amounts, estimated City of Houston shares, and the total projected costs for each project.
|
Project
|
Council District
|
Project Type
|
Funding Request
|
Estimated City of Houston Share
|
Total Projected Cost
|
|
Alief Forest South Area Drainage and Paving
|
F
|
Capital
|
$7,000,000.00
|
$12,200,000.00
|
$19,200,000.00
|
|
Lakeside Estates Dr. Street Rehabilitation
|
G
|
Capital
|
$2,100,000.00
|
$900,000.00
|
$3,000,000.00
|
|
Total
|
|
|
$9,100,000.00
|
$13,100,000.00
|
$22,200,000.00
|
FISCAL NOTE:
No significant fiscal operating impact is anticipated as a result of this project.
___________________________
Randall V. Macchi, JD