Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/21/2025
District B, District H, District I, District K
Item Creation Date: 8/6/2025

HPW - 20FAC2603 Accept Work / Main Lane Industries, LTD

Agenda Item#: 6.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works that Houston City Council accept the work and authorize final payment, if any, of the contract with MAIN LANE INDUSTRIES, LTD for Rehabilitation of Above Grade Crossings Package 2 - DISTRICTS B - JACKSON; H - CASTILLO; I - MARTINEZ and K - CASTEX-TATUM

Background:

SUBJECT: Accept Work for Rehabilitation of Above Grade Crossings Package 2.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final contract amount of $2,821,315.49 or 0.52% under the original contract amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project required to repair or replace large diameter water lines to minimize the impacts of major water main shutdowns.

 

DESCRIPTION/SCOPE: This project consisted of replacing two aerial crossings; one at Tidwell Road and Halls Bayou (Site 3) by new aerial crossing and one near West Orem Drive and Harris County Flood Control District (HCFCD) C157-00-00 (Site 18). The project also included the coating rehabilitation of two existing aerial crossings at 69th Street and Buffalo Bayou (Site 22). Lockwood, Andrews & Newnam, Inc. designed the project with 730 calendar days allowed for construction. The project was awarded to Main Lane Industries, Ltd with an original contract amount of $2,836,035.00.

 

LOCATION:

PROJECT NAME

LOCATION

COUNCIL DISTRICT

Rehabilitation of Above Grade

Crossings - Package 2

Tidwell Road at Halls Bayou

(Site 3)

B

Rehabilitation of Above Grade

Crossings - Package 2

West Orem Drive and HCFCD

C157-00-00 (Site 18)

K

Rehabilitation of Above Grade

Crossings - Package 2

69th Street at Buffalo Bayou

(Site 22)

H, I

 

CONTRACT COMPLETION AND COST: The contractor, Main Lane Industries, Ltd, has completed the work under the subject contract. The project was completed beyond the established completion date with an additional 330 days approved by Change Order No. 4. The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos. 1, 2, and 3 is $2,821,315.49, a decrease of $14,719.51 or 0.52% under the original contract amount and under the 5% contingency amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised MWSBE contract goals for this project were 12.00% MBE and 7.00% WBE. The MWSBE goals approved for this project were 12.00% MBE, 3.00% WBE and 4.00% SBE. According to the Office of Business Opportunity, the actual participation achieved on this project was 11.32% MBE, 3.15% WBE and 6.93% SBE. The MWSBE performance on this project was rated Outstanding for the following reasons: The WBE and SBE goals were exceeded and MBE participation was within 1% of the awarded goal, and all goal credit subcontractors were utilized to the extent possible. For the reasons listed, the MWSBE performance meets the good faith efforts requirements mandated by the City's MWSBE Program.

 

 

 

________________________________

Randall V. Macchi, JD

Director, Houston Public Works

 

WBS No. S-000701-0024-4

Prior Council Action:

Ordinance No. 2022-0168, dated 03-02-2022

Amount and Source of Funding:

No additional funding required.

 

Original appropriation from $3,269,635.00 - Fund No. 8500 – Water and Sewer System Consolidated Construction  Fund

 

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Assistant Director

DO-HPW Council Liaison Office

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Council Liaison Office

832.395.2282

Markos Mengesha, Assistant Director

HPW-Facilities Delivery Line

832.395.2365