SUBJECT: Accept Work for Sanitary Sewer Rehabilitation by Sliplining and Pipe Bursting Methods - PM Construction & Rehab, L.P. - WBS# R-000266-0167-4
RECOMMENDATION: (Summary) Pass a motion to approve the final contract amount of $3,258,232.29, which is 0.70% over the original contract amount and under the 5% contingency amount, accept the work, and authorize final payment.
PROJECT NOTICE/JUSTIFICATION: Under this project, the contractor provided sanitary sewer rehabilitation by sliplining and pipe bursting methods to deteriorated sewer collection systems throughout the City.
DESCRIPTION/SCOPE: This project consisted of sanitary sewer rehabilitation by sliplining and pipe bursting methods. The project was awarded to PM Construction & Rehab, L.P. with an original contract amount of $3,235,430.61. The Notice to Proceed date was 09/22/2011 and the project had 540 calendar days for completion.
LOCATION: The work order project area was located at various locations within Council Districts B, I and K.
CONTRACT COMPLETION AND COST: The contractor, PM Construction & Rehab, L.P., has completed the work under the contract. The contract was completed within the contract time. The final cost of the project is $3,258,232.29, an increase of $22,801.68 or 0.70% over the original contract amount. More point repairs were needed than anticipated.
The final amount of this work order contract was not affected by Change Order No. 1 and No. 2.
MWDBE PARTICIPATION: The MWDBE goal for this project was 21%. According to the Office of Business Opportunity, the actual participation was 29.69%. The contractor was awarded an “Outstanding” rating from the Office of Business Opportunity.