SUBJECT: Accept Work for Sanitary Sewer Rehabilitation by Sliplining and Pipe Bursting Methods - PM Construction & Rehab, L.P. - WBS# R-000266-0151-4.
RECOMMENDATION: (Summary) Pass a motion to approve the final contract amount of $3,160,308.18, which is 0.50% under the original contract amount, accept the work, and authorize final payment.
SPECIFIC EXPLANATION:
PROJECT NOTICE/JUSTIFICATION: Under this project, the contractor provided sanitary sewer rehabilitation by sliplining and pipe bursting methods to deteriorated sewer collection systems throughout the City.
DESCRIPTION/SCOPE: This project consisted of sanitary sewer rehabilitation by sliplining and pipe bursting methods. The project was awarded to PM Construction & Rehab, L.P. with an original contract amount of $3,176,336.30. The Notice to Proceed date was 03/24/2011 and the project had 540 calendar days for completion.
LOCATION: The work order project area was located at various locations within Council Districts A, B, C, E, I and K.
CONTRACT COMPLETION AND COST: The contractor, PM Construction & Rehab, L.P., has completed the work under the contract. The contract was completed within the contract time. The final cost of the project is $3,160,308.18, a decrease of $16,028.12 or 0.50% under the original contract amount. Less pipe bursting was needed than anticipated.
The final amount of this work order contract was not affected by Change Order No. 1 and No. 2.
MWDBE PARTICIPATION: The MWDBE goal for this project was 21%. According to the Office of Business Opportunity, the actual participation was 31.45%. The contractor was awarded an “Outstanding” rating from the Office of Business Opportunity.