HPW - 20INF2538 Additional Appropriation / Halff Associates, Inc.
Agenda Item#: 28.
| |
|
| | | | | | | | Summary:
ORDINANCE appropriating $5,643,750.00 out of Dedicated Drainage and Street Renewal Capital Fund – Drainage Charge as additional appropriation to Professional Engineering Services Contract between City of Houston and HALFF ASSOCIATES, INC for Professional Services and Technical Support for Paving and Drainage Projects (as approved by Ordinance No. 2020-0907); providing funding for CIP Cost Recovery relating to construction of facilities financed by the Dedicated Drainage and Street Renewal Capital Fund – Drainage Charge |
| | | | | | | | Background:
SUBJECT: Third Additional Appropriation for the Professional Engineering Services Contract between the City and Halff Associates, Inc. for Professional Services and Technical Support for Paving and Drainage Projects.
RECOMMENDATION: Approve an ordinance appropriating additional funds to the Professional Engineering Services Contract with Halff Associates, Inc.
PROJECT NOTICE/JUSTIFICATION: This project is part of the Storm Drainage Capital Improvement Plan (CIP) and is required to assist the City with implementation of drainage and paving improvement projects to reduce the risk of structural flooding.
DESCRIPTION/SCOPE: This project consists of project management and staff augmentation, technical services and support, and engineering design services. The specific scope, budget, and schedule shall be established for each separate work order prior to authorization of the project by the City.
LOCATION: The projects are located throughout the City of Houston.
PREVIOUS HISTORY AND SCOPE: City Council approved the original contract on October 21, 2020 under Ordinance No. 2020-0907. The scope of services under the original contract consisted of project management, staff augmentation, and technical support services for paving and drainage projects. Under this contract, the Consultant has accomplished the scope of service.
Ord. No.
|
Ord. Date
|
Type
|
Scope of the Action
|
Accomplished to Date
|
2022-0147
|
02-23-2022
|
Amend
|
Project management, staff augmentation, and technical support services for paving and drainage projects.
|
Contract services and the addition of Texas Water Development Board grant funds for the Storm Water Master Plan program management and one model.
|
2023-0800
|
09-27-2023
|
Add
|
Continue providing project management, staff augmentation, and technical support as needed for contract services.
|
Project management, staff augmentation, and technical support.
|
SCOPE OF THIS ADDITIONAL APPROPRIATION AND FEE: Under the scope of the Third Additional Appropriation, the Consultant will continue providing project management, staff augmentation, and technical support as needed for contract services.
The total requested appropriation is $5,643,750.00 to be appropriated as follows: $5,375,000.00 for contract services and $268,750.00 for CIP Cost Recovery.
PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City Contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.
M/WBE PARTICIPATION: The M/WBE goal established for this project is 24%. The original contract amount and subsequent appropriations total $17,728,880.00. The Consultant has been paid $14,258,487.00 (80.43%). Of this amount, $4,317,892.00 (30.28%) has been paid to M/WBE sub-contractors to date. Assuming approval of the requested additional appropriation, the contract amount will increase to $23,103,880.00. The MWBE goal has been previously met.
Name of Firms
|
Work Description
|
Amount
|
% of Total Contract
|
Paid Prior M/WBE Commitment
|
|
$4,317,382.00
|
18.69%
|
Unpaid Prior M/WBE Commitment
|
|
$ 242,108.00
|
1.05%
|
1. Amani Engineering, Inc.
|
Engineering services
|
$ 150,000.00
|
0.65%
|
2. HVJ Associates, Inc.
|
Engineering services
|
$ 50,000.00
|
0.22%
|
3. Trilogy Engineering Services, LLC
|
Business Management
consulting services
|
$ 200,000.00
|
0.87%
|
4. Civitas Engineering Group, Inc.
|
Engineering services
|
$ 850,000.00
|
3.68%
|
5. Ardurra Group, Inc. dba Gunda Corporation, LLC
|
Engineering,
Administrative
Management, and
Construction
Management
|
$ 150,000.00
|
0.65%
|
|
TOTAL
|
$5,959,490.00
|
25.81%
|
FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.
_________________________________
Randall V. Macchi, JD
Director, Houston Public Works
WBS No. M-430220-0040-3 |
| | | | | | | | Prior Council Action:
Ordinance No. 2020-0907, dated 10-21-2020
Ordinance No. 2022-0147, dated 02-23-2022
Ordinance No. 2023-0800, dated 09-27-2023 |
| | | | | | | | Amount and Source of Funding:
$5,643,750.00 from Fund No. 4042 - Dedicated Drainage and Street Renewal Capital Fund – Drainage Charge
Original (previous) appropriation of $6,081,761.70 from Fund No. 4042 – Dedicated Drainage and Street Renewal Capital Fund – Drainage Charge
Subsequent appropriation: Total: $6,884,000.00
$2,362,500.00 - Fund No. 5410 -State Grant Funded - DDSRF
$787,500.00 - Fund No. 4042 - Dedicated Drainage and Street Renewal Capital Fund – Drainage (Grant Fund Match)
$3,734,000.00 - Fund No. 4042 - Dedicated Drainage and Street Renewal Capital Fund - Drainage Charge
Second subsequent appropriation of $5,649,783.00 from Fund No. 4042 - Dedicated Drainage and Street Renewal Capital Fund – Drainage Charge
|
| | | | | | | | Contact Information:
Name
|
Service Line
|
Contact No.
|
Roberto Medina, Assistant Director
|
DO-HPW Council Liaison Office
|
832.395.2456
|
Maria Perez, HPW Agenda Coordinator
|
DO-HPW Council Liaison Office
|
832.395.2282
|
Tanu Hiremath, P.E., CFM, ENV SP Assistant Director
|
HPW-Infrastructure Delivery Line
|
832-395-2291
|
|
|