Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/24/2025
District D, District G
Item Creation Date: 4/9/2025

HPW – 20FAC2547 Amendment / CP&Y, Inc. dba STV Infrastructure

Agenda Item#: 27.


 
                               
Summary:

ORDINANCE appropriating $180,000.00 out of Water & Sewer System Consolidated Construction Fund; approving and authorizing first amendment to Professional Engineering Services Contract between City of Houston and CP&Y, INC dba STV INFRASTRUCTURE for Lift Station Renewal and Replacement (Approved by Ordinance No. 2013-0489); providing funding for CIP Cost Recovery relating to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund - DISTRICTS D - EVANS-SHABAZZ and G - HUFFMAN

Background:

SUBJECT: First Amendment to the Professional Engineering Services Contract between the City and CP&Y, Inc. dba STV Infrastructure for Lift Station Renewal and Replacement.

 

RECOMMENDATION: Approve the First Amendment to the Professional Engineering Services Contract with CP&Y, Inc. dba STV Infrastructure and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the City’s ongoing program to upgrade its wastewater lift stations facilities.

 

DESCRIPTION/SCOPE:  The scope of work includes the overall condition assessment/evaluation of the five lift stations listed below, and to provide recommended alternatives and prepare the complete design packages for each lift station.

 

LOCATION:

 

PROJECT NAME

LOCATION

COUNCIL DISTRICT

Braeswood North 

2702 N. Braeswood

C

MacGregor Way North No. 1

2000 N. Macgregor Way

D

Magnet

2710 Magnet

D

Westpark No. 1 4307 Westpark Dr. G
Kirby Drive No. 1 8500 Kirby Drive K

 

PREVIOUS HISTORY AND SCOPE: City Council approved the original contract on May 29, 2013 under Ordinance No. 2013-0489. The scope of services under the original contract consisted of  Phase I – preliminary design, Phase II – final design, and Phase III – construction phase services and additional services. Under this contract, the Consultant has accomplished Phase I – preliminary design, Phase II – final design, and 90% of Phase III – construction phase services.

 

SCOPE OF THIS AMENDMENT AND FEE: Under the scope of the First Amendment, the Consultant will accomplish the following: New Design for transformer pad and duct banks at MacGregor Way North No. 1, Magnet, and Westpark No. 1 Lift Stations.  A fee of $171,000.00 is budgeted for Basic Services.

 

The total requested appropriation is $180,000.00 to be appropriated as follows: $171,000.00 for contract services and $9,000.00 for CIP Cost Recovery.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City Contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

 

M/WBE PARTICIPATION: The M/WBE goal established for this project is 24.00%. The original contract amount and subsequent appropriation total $1,281,735.00. The Consultant has been paid $1,158,174.00 (90.36%). Of this amount, $226,450.00 (19.55%) has been paid to M/WBE sub-contractors to date. Assuming approval of the requested additional appropriation, the contract amount will increase to $1,452,735.00. The Consultant proposes the following plan to meet the M/WBE goal.

 

 

Name of Firms

Work Description

Amount

% of Total Contract

Paid Prior M/WBE Commitment

 

$226,450.00

15.59%

Unpaid Prior M/WBE Commitment

 

$  81,166.00

  5.59%

1. Amani Engineering, Inc

Engineering services

$  34,033.28

  2.34%

2. Associated Testing Laboratories, Inc.

Engineering services

$    7,000.00

  0.48%

 

TOTAL

$348,638.28

24.00%

 

 

 

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

 

_________________________________

Randall V. Macchi, JD

Director, Houston Public Works

 

WBS No. R-000267-0118-3

 

Prior Council Action:

Ordinance No. 2013-0489, dated 05-29-2013

Amount and Source of Funding:

Total $180,000.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund

 

Original appropriation of $1,474,000.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund.

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Assistant Director

DO-HPW Council Liaison Office

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Council Liaison Office

832.395.2282

Markos E. Mengesha, P.E., CCM, Assistant Director

HPW- Facilities Delivery Line

832-395-2365


ATTACHMENTS:
DescriptionType
Signed coversheetSigned Cover sheet
MapsBackup Material