Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/7/2025
District A, District B, District D, District E, District G, District H, District I
Item Creation Date: 3/18/2025

HPW – 20FAC2565 PES / Arcadis U.S., Inc.

Agenda Item#: 44.


 
                               
Summary:

ORDINANCE appropriating $2,466,585.45 out of Water & Sewer System Consolidated Construction Fund; approving and authorizing Professional Engineering Services Contract between City of Houston and ARCADIS U.S., INC for Large Diameter Water Line and Above Grade Crossings – Package #3; providing funding for CIP Cost Recovery financed by the Water & Sewer System Consolidated Construction Fund - DISTRICTS A - PECK; B - JACKSON; D - EVANS-SHABAZZ; E - FLICKINGER; G - HUFFMAN and I - MARTINEZ

Background:

SUBJECT: Professional Engineering Services Contract between the City and Arcadis U.S., Inc. for Large Diameter Water Line and Above Grade Crossings – Package 3.

 

RECOMMENDATION:  An ordinance approving a Professional Engineering Services Contract with Arcadis U.S., Inc.  for Large Diameter Water Line and Above Grade Crossings – Package 3 and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the City’s Water Line Replacement Program and is required to replace and upgrade water lines for the increase of water availability, circulation improvement, and fire protection.

 

 DESCRIPTION/SCOPE: This project consists of the design of water line replacements and upgrades with all related appurtenances.

 

LOCATION:   The projects are located throughout the City of Houston.

 

SCOPE OF CONTRACT AND FEE: Under the scope of the Contract, the Consultant will perform Phase I - Preliminary Design, Phase II Final Design, Phase III - Construction Phase Services and Additional Services. Basic Services Fee for Phase I is based on cost of time and materials with a not-to-exceed agreed upon amount. The Basic Services fees for Phase II and Phase III are based on a negotiated lump sum amount. The total Basic Services appropriation is $1,331,129.00.

 

The Contract also includes certain Additional Services to be paid either as a lump sum or on a reimbursable basis. The total Additional Services appropriation is $1,018,000.00.

 

The negotiated maximum for Phase I Services is $306,664,00.

 

The total cost of this project is $2,466,585.45 to be appropriated as follows: $2,349,129.00 for Contract services and $117,456.45 for CIP Cost Recovery.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Consultant provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION: The standard M/WBE goal set for the project is 26.00%. The Consultant has proposed a 35.84% MWBE plan to meet the goal.

 

 

Name of Firms

Work Description

    Amount

      % of Total             Contract

1.

Amani Engineering, Inc.

Engineering services/Land surveying services

$189,963.00

8.09%

2.

Aurora Technical Services LLC

Construction management, Engineering services

$324,974.70

              13.83%

3.

Aviles Engineering Corporation

Construction management, Engineering consulting services

$156,991.50

6.68%

4.

Nedu Engineering Services, Inc

Construction management, Engineering services

$  39,150.00

1.67%

5.

V & A Consulting Engineers, Inc.

Engineer’s offices

$130,924.80

5.57%

 

 

TOTAL

$842,004.00

              35.84%

 

 

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

____________________________

Randall V. Macchi, JD

Director, Houston Public Works

 

WBS No. S-000701-0049-3

 

Amount and Source of Funding:

$2,466,585.45 from Fund No. 8500 – Water and Sewer System Consolidated Construction

 

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Assistant Director

DO-HPW Council Liaison Office

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Council Liaison Office

832.395.2282

Markos E. Mengesha, P.E., CCM, Assistant Director

HPW-Facilities Delivery Line

832-395-2365


ATTACHMENTS:
DescriptionType
Signed coversheetSigned Cover sheet
Project Location ListBackup Material