Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 5/20/2025
ALL
Item Creation Date: 2/28/2025

HPW – 20SWO192 Contract Award / J. Rivas Construction LLC

Agenda Item#: 46.


 
                               
Summary:

ORDINANCE awarding contract to J. RIVAS CONSTRUCTION LLC for FY 2025 Ditch Reestablishment Work Order Contract #3; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing a maximum contract amount - $6,000,000.00 - Enterprise Fund

Background:

SUBJECT: Contract Award for FY2025 Ditch Re-establishment Work Order Contract #3.
 
RECOMMENDATION: (SUMMARY) Award a Construction Contract to J. Rivas Construction LLC for FY2025 Ditch Re-establishment Work Order Contract #3 with a maximum contract amount not-to-exceed $6,000,000.00 and allocate funds. 
 
PROJECT NOTICE/JUSTIFICATION: This project is part of the Transportation and Drainage Operations Program and is required to provide work authorization on a location-by-location as-needed basis, for the operation and maintenance of stormwater drainage assets. 

 

DESCRIPTION/SCOPE: This project consists of the Citywide program that provides maintenance services for open drainage systems. The scope is established by each work authorization. The Contract duration for this project is 730 calendar days.  
 
LOCATION: The projects are located throughout the City of Houston. 
 
PROPOSAL: This project was advertised for competitive sealed proposals on September 20, 2024. Proposals were received on October 10, 2024. The proposals received  are as follows:

 

   Proposer   Adjustment Factor   
 1.   J. Rivas Construction, LLC    0.497  
 2.  DL Glover Utilities    0.500  
 3.  Grava, LLC     0.615  
 4.  T Construction LLC    0.675  
         
 

AWARD: A Selection Committee was comprised of members from Houston Public Works, General Services Department, and Houston Airport SystemThe Selection Committee reviewed the proposals and recommended that this construction contract be awarded to J Rivas Construction, LLC. based on their Qualifications, Project Approach, Total Proposal Price, Financial Capabilities, Experience, Safety, and Hire Houston First Designation with a total proposal bid price of $6,000,000.00 (0.497 Adjustment Factor).

 

It is recommended that this construction contract be awarded to J. Rivas Construction, LLC with a proposal of $6,000,000.00 (0.497 Adjustment Factor).

 

PROJECT COST: The total cost of this project is as follows: 

 
                             Proposal Amount                    $6,000,000.00   
         

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case, J. Rivas Construction LLC is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 18.00% MBE goal and 5.00% WBE goal for this project. 

 

  MBE - Name of Firms     Work Description    Amount   % of Contract   
 1. D. Solis Trucking, Inc.  

Dump Trucking

   $   390,000.00  

      6.50%

 
 2. J. Rivas Construction LLC  

Ditch Re-establishment

   $   690,000.00       11.50%  
                 
  WBE - Name of Firms    Work Description    Amount    % of Contract  
 1. J & A Trucking Services LLC  

Asphalt Paving

   $   300,000.00         5.00%  
       TOTAL    $1,380,000.00       23.00%  
                 
 

FISCAL NOTE:  Funding for this item is included in the FY2025 Adopted Budget. Therefore, no Fiscal Note is required as stated in the Financial Policies.

 

 

 

 

_________________________________ 

Randall V. Macchi, J.D.
Director, Houston Public Works 
 
WBS No. M-43M009-0011-4

 

 

Estimated Spending Authority

Department

Current FY25

Out Year 1

Total

Houston Public Works

$500,000.00

$5,500,000.00

$6,000,000.00

Amount and Source of Funding:

$6,000,000.00 from Fund No. 2302 – Stormwater Fund

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Assistant Director

DO-HPW Council Liaison Office

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Council Liaison Office

832.395.2282

Fabio Capillo, Deputy Director

HPW Transportation & Drainage Operations

832.395.6685


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet