Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/3/2024
ALL
Item Creation Date: 10/28/2024

HPW - 20PMO148 PES / Gradient Group, LLC

Agenda Item#: 46.


 
                               
Summary:

ORDINANCE appropriating $550,000.00 out of Metro Projects Construction DDSRF and approving and authorizing Professional Engineering Services Contract between City of Houston and GRADIENT GROUP, LLC for FY24 Street Rehabilitation Design Projects Contract #1; providing funding for CIP Cost Recovery relating to construction of facilities financed by the Metro Projects Construction DDSRF

Background:

SUBJECT: Professional Engineering Services Contract between the City of Houston (COH) and Gradient Group, LLC for FY24 Street Rehabilitation Design Projects Contract #1.

 

RECOMMENDATION:  An ordinance approving a Professional Engineering Services Contract with Gradient Group, LLC. for FY24 Street Rehabilitation Design Projects Contract #1, and appropriate funds.

 

 PROJECT NOTICE/JUSTIFICATION: This project is part of the Street Rehabilitation program and is needed to meet COH design and safety standards and improve streets.

 

 DESCRIPTION/SCOPE: Provide engineering services to Houston Public Works for Street Rehabilitation.  Engineering Services may include topographic survey, data collection, agency coordination, geotechnical investigations, ADA pedestrian element evaluations and recommendations, field pavement assessments, construction and treatment plan preparation, cost estimation, and construction phase services, as requested. The proposed Street Rehabilitation will be designed and constructed in compliance with City of Houston Infrastructure Design Manual, Texas Manual of Uniform Traffic Control Devices (TX MUTCD), Americans with Disability Act (ADA) and Texas Accessibility Standard (TAS). Projects will be assigned on a work order basis.

 

LOCATION: The projects are located throughout the City of Houston.

 

SCOPE OF CONTRACT AND FEE: Under the scope of the contract, the Consultant will perform the following:

  • conduct existing condition surveys on selected streets segments and produce street base maps
  • identify drainage and base failures and provide possible solutions within COH latest edition standards
  • identify potential landscape and utilities within the right-of-way
  • identify COH right-of-way, and provide boundary survey when right-of-way acquisition is required
  • design required geometric improvements to roadways and ADA compliant wheelchair ramps
  • develop construction documents for required street segments, prepare plans, special specifications, general notes, COH typical drawings, quantity take offs and construction estimates as requested

 

The total requested appropriation is $550,000.00 to be appropriated as follows: $500,000.00 for contract services and $50,000.00 for CIP Cost Recovery.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Consultant provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION: The standard M/WBE goal set for the project is 29.00%. The Consultant has proposed a 49.00 % MWBE plan.

    

 

 

Name of Firms

Work Description

Amount

% of Total Contract

 

1.

Asakura Robinson

Company LLC

Landscaping/Tree Protection

$ 15,000.00

3.00%

 

 

 

2.

CJ Hensch & Associates, Inc.

 

Traffic Data Collection

$ 10,000.00

2.00%

 

 

3.

Cypress Environmental Consulting LLC

Environmental

 

$ 25,000.00

5.00%

 

 

4.

 

 

Geotest Engineering, Inc.

 

Engineering Services

(Geotechnical Services)

$ 25,000.00

5.00%

 

 

5.

 

6.

 

7.

 

KUO & Associates, Inc.

 

 

Stevens Technical Services, Inc.

 

 

Gradient Group, LLC

Surveying

 

 

 

Signal Design RAS / ADA Compliance

 

 

Engineering Design Services

TOTAL

$ 50,000.00

 

 

 

$50,000.00

 

 

$ 70,000.00

 

$245,000.00

10.00%

 

 10.00%

 

          14.00%

          49.00%

 

                                                               

 

 FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

 

_________________________________

Randall V. Macchi

Chief Operating Officer

Houston Public Works

 

 

 

WBS No N-321040-0113-3

Amount and Source of Funding:

$550,000.00

METRO Projects Construction DDSRF

Fund No. 4040

Contact Information:
 

Name

Service Line

Contact No.

Roberto Medina, Interim Chief of Staff

DO-HPW Government Relations

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Government Relations

832.395.2282

Michael Wahl, Assistant Director

TDO

832.395.2443

 


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet