Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/17/2024
ALL
Item Creation Date: 10/7/2024

HPW-20PMO168 / Contract Award / JFT Construction, Inc.

Agenda Item#: 45.


 
                               
Summary:

ORDINANCE appropriating the sum of $16,283,446.10 out of the Metro Projects Construction - DDSRF; awarding a Contract to JFT CONSTRUCTION, INC. for FY2025 Citywide Concrete Panel Replacements Project #2; setting a deadline for the bidder’s execution of the Contract and delivery of all bonds, insurance, and other required Contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for testing services and CIP Cost Recovery relating to construction of facilities financed by the Metro Projects Construction - DDSRF

Background:

 

SUBJECT:  Contract Award for FY2025 Citywide Concrete Panel Replacements Project #2.

 

RECOMMENDATION: (SUMMARY) Accept low bid, award construction contract for FY2025 Citywide Concrete Panel Replacements Project #2 to JFT Construction, Inc., and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the Roadway Rehabilitation Program and will provide work order on a location-by-location basis, as needed, to provide construction services to include but not limited to the construction repair, rehabilitation, removal, disposal, and/or replacement of roadway pavement and other pavement related improvements.

 

DESCRIPTION/SCOPE: This Citywide program provides construction services to include but not limited to the construction repair, rehabilitation, removal, disposal, and/or replacement of roadway pavement and other pavement related improvements. The Contract duration for this project is 730 calendar days.

 

 

LOCATION: The projects are located throughout the City of Houston.

 

BIDS: This project was advertised for bidding on July 12, 2024 and July 19, 2024. Bids were received on July 25, 2024. The five (5) bids are as follows:

 

 

Bidder

Bid Amount

1.

JFT Construction, Inc

$14,484,951.00

 

2.

Tikon Group, Inc.

$16,711,560.00

 

3.

Grava, LLC

$18,192,528.80

 

4.

Total Contracting Limited

$19,491,411.00

 

5.

MC2 Civil, LLC

$20,731,420.00

 

 

 

AWARD: It is recommended that this construction contract be awarded to JFT Construction, Inc. with a low bid of $14,484,951.00.

 

 

PROJECT COST: The total cost of this project is $16,283,446.10 to be appropriated as follows:

 

·         Bid Amount                                                  $14,484,951.00

·         Testing Services                                               $350,000.00

·         CIP Cost Recovery                                        $1,448,495.10

                       

Testing Services will be provided by Terracon Consultants, Inc., under a previously approved contract.

 

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case JFT Construction, Inc. is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City Policy.

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the  13.00% MBE goal and 7.00% WBE goal for this project.

 

 

MBE Name of Firms

Work Description

Amount

% of Contract

1.

Match & Mix Construction LLC

Concrete Work

$1,883,043.63

13.00%

SBE Name of Firms

Work Description

Amount

% of Contract

1.

Professional Traffic Control LLC

Striping Services

$579,398.04

4.00%

WBE Name of Firms

Work Description

Amount

% of Contract

1.

Access Data Supply, Inc.

Ready Mix Concrete

$434,548.53

3.00%

TOTAL

$2,896,990.20

20.00%

 

 

 

FISCAL NOTE:  No significant Fiscal Operating Impact is anticipated as a result of this project.

 

 

______________________________

Randall V. Macchi

Director

Houston Public Works

 

 

WBS No. N-321040-0128-4

Amount and Source of Funding:

$16,283,446.10

 METRO Projects Construction - DDSRF

Fund No. 4040 

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Interim Chief of Staff

DO-HPW Government Relations

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Government Relations

832.395.2282

Michael Wahl, Deputy Director

TDO

832.395.2443

 


ATTACHMENTS:
DescriptionType
MapsBackup Material
Signed CoversheetSigned Cover sheet