HPW – 20FAC2510 Accept Work / Vadnais Trechless Services, Inc.

Agenda Item#: 6.


 
                               
Summary:

RECOMMENDATION from Chief Operating Officer, Houston Public Works, for approval of final contract amount of $15,233,742.81 and acceptance of work on contract with VADNAIS TRENCHLESS SERVICES, INC for Abandonment and Flow Diversion of Interwood, M.U.D. #266 and Vickery Lift Stations - 2.15% over the original contract amount - DISTRICT B - JACKSON

Background:

SUBJECT:  Accept Work for Abandonment and Flow Diversion of Interwood, M.U.D. #266, and Vickery Lift Stations.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $15,233,742.81 or 2.15% over the original Contract Amount, accept the Work, and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION:  This project was part of the City’s Capital Improvements Plan (CIP) for wastewater facilities.

 

DESCRIPTION/SCOPE: This project consisted of abandonment and flow diversion of three Lift Stations, furnishing and installation of multiple size sanitary sewers by trenchless method and a sanitary sewer by open cut method, along with associated manholes as shown in the construction drawings. The scope also included traffic control in relation to the construction of the sanitary sewers. Arcadis U.S. Inc. designed the project with 556 calendar days allowed for construction. The project was awarded to Vadnais Trenchless Services, Inc., with an original Contract Amount of $14,912,791.92.

 

LOCATION: The projects are in 3 locations. 

 

Lift Station Project

LOCATION

COUNCIL DISTRICT

Vickery 

15479 Vickery Drive

B

Interwood 

4150 Aldine Bender Road

B

M.U.D #266

15021 Crosswinds Drive

B

 

CONTRACT COMPLETION AND COST: The Contractor, Vadnais Trenchless Serivces, Inc., has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 153 days approved by Change Order Nos 1,3,4,5,7 and 8. The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos 1,2,6,7, and 8 is $15,233,742.81, an increase of $320,950.89 or 2.15% over the original Contract. The increased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION:  The advertised M/WBE contract goals for this project were 13.00% MBE and 7.00% WBE. The M/W/SBE goals approved for this project were 14.17% MBE, 11.85% WBE, and 0.83% SBE. According to the Office of Business Opportunity, the actual participation achieved on this project was 12.32% MBE, 11.80% WBE, and 1.36% SBE. The MWSBE performance on this project was rated Satisfactory for the following reasons: the advertised WBE goal was exceeded and advertised MBE goal was within 1% of being met, while additional goal credit was achieved through SBE participation and the utilization of goal credit subcontractors to the extent possible. For the reasons listed, the MWSBE performance meets the good faith efforts requirements mandated by the City's MWSBE Program.

 

 

 

 

______________________________________

Randall V. Macchi, Chief Operating Officer

Houston Public Works

 

WBS No. R-000267-121B-4

Prior Council Action:

Ordinance No. 2019-0650, dated 08-21-2019

Amount and Source of Funding:

No additional funding required.

Total (original) appropriation of $18,151,710.92 from Fund No. 8500- Water and Sewer System Consolidated Construction.

 

 

 

 

 

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Interim Chief of Staff

DO-HPW Government Relations

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Government Relations

832.395.2282

Markos E. Mengesha, Assistant Director

FAC-HPW Capital Projects

832.395.2291


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
Maps Backup Material