CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/24/2024
District A, District D, District J
Item Creation Date: 8/19/2024

HPW – 20WWO1147 Accept Work / LEM Construction Company, Inc.

Agenda Item#: 3.


 
                               
Summary:

RECOMMENDATION from Chief Operating Officer, Houston Public Works for approval of final contract amount of $2,483,377.42 and acceptance of work on contract with LEM CONSTRUCTION COMPANY, INC for Keegans Bayou, Northwest and Chocolate Bayou Wastewater Treatment Plants (WWTP) Bar Screen and Grating Replacement - 4.88% under the original contract amount - DISTRICTS A - PECK; D - EVANS-SHABAZZ and J - POLLARD

Background:

SUBJECT: Accept Work for Keegans Bayou, Northwest and Chocolate Bayou Wastewater Treatment Plants (WWTP) Bar Screen and Grating Replacement.

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final contract amount of $2,483,377.42 or 4.88% under the original contract amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s ongoing program to improve inefficient components of the existing wastewater treatment plant facilities. 

 

DESCRIPTION/SCOPE: This project consisted of 1. Rehabilitation of the walkway grating and grating support system at the influent and effluent aeration basin channels at the Keegans Bayou WWTP; 2. Removal and replacement of the bar screens, conveyor system as well as associated electrical, control and ancillary equipment at the Keegans Bayou, Northwest and Chocolate Bayou WWTPs. HR Green Inc. designed the project with 270 calendar days allowed for construction. The project was awarded to LEM Construction Company, Inc. with an original contract amount of $2,610,750.00.

 

LOCATION:

FACILITY NAME

LOCATION

COUNCIL DISTRICT

Northwest WWTP

5423 Mangum Road, 77091

A

Chocolate Bayou WWTP

9600 Martin Luther King Blvd, 77048

D

Keegans Bayou WWTP

9400 White Chapel Lane, 77074

J

 

CONTRACT COMPLETION AND COST: The contractor, LEM Construction Company, Inc., has completed the work under the subject contract. The project was completed beyond the established completion date with an additional 267 days approved by Change Order No 1, 2 and 3. The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order No. 1 is $2,483,377.42, a decrease of $127,372.58 or 4.88% under the original contract amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised M/WBE contract goals for this project were 11% MBE, and 7% WBE. The M/WSBE goals approved for this project were 9.96% MBE, 7.22% WBE and 8.43% SBE. According to the Office of Business Opportunity, the actual participation achieved on this project was 10.62% MBE, 7.59% WBE and 8.86% SBE. The MWSBE performance on this project was rated Satisfactory for the following reasons: the MBE, WBE, and the SBE goals were met and all goal credit subcontractors were used to full capacity. For the reasons listed, the MWSBE performance meets the good faith efforts requirements mandated by the City's MWSBE Program.

 

 

 

_________________________________

Randall V. Macchi, Chief Operating Officer

Houston Public Works

 

WBS No. R-000265-144B-4

Prior Council Action:

Ordinance No. 2021-0087, dated 02-03-2021

Amount and Source of Funding:

No additional funding required.

 

Original appropriation of $2,871,825.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund.

 

 

 

 

 

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Interim Chief of Staff

DO-HPW Government Relations

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Government Relations

832.395.2282

Joseph Majdalani, Senior Assistant Director

HPW Houston Water

832-395-8530

 

ATTACHMENTS:
DescriptionType
Signed Coversheet Signed Cover sheet
MapsBackup Material