Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/15/2024
District A, District C, District D, District G, District H, District I
Item Creation Date: 6/12/2024

20SWO168 Accept Work / J Rivas Construction, LLC

Agenda Item#: 9.


 
                               
Summary:

RECOMMENDATION from Chief Operating Officer, Houston Public Works, for approval of final contract amount of $4,056,333.74 and acceptance of work on contract with J. RIVAS CONSTRUCTION, LLC for FY 2022 Street & Drainage Rehabilitation Contract #3 - 1.41% over the original Contract Amount and under the 5% contingency amount - DISTRICTS A - PECK; C - KAMIN; D - EVANS-SHABAZZ; G - HUFFMAN; H - CASTILLO and I - MARTINEZ

Background:

SUBJECT: Accept Work for FY 2022 Street & Drainage Rehabilitation Contract #3.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $4,056,333.74 or 1.41% over the original Contract Amount, accept the Work, and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the Transportation and Drainage Operations Program which provides work authorizations on a location-by-location as-needed basis, to preserve, repair, rehabilitate, and reconstruct the stormwater drainage asset including street rehabilitation to a condition that it may be effectively used for its designated functional purpose.

 

DESCRIPTION/SCOPE: This project consisted of the Citywide program that provided construction services to resolve localized stormwater drainage problems and rehabilitate the street to further improve drainage. The time allotted for this project was 730 calendar days. The project was awarded to J Rivas Construction, LLC with an original Contract Amount of $4,000,000.00.

 

LOCATION: The projects are in 8 locations.

 

Work Authorization

LOCATION

COUNCIL DISTRICT

1

2401 Maroneal Street

C

2

6414 Reed Road

I

3

BastropStreet and Bell Street

I

4

4500 Wilmington Street

D

5

701 E 6 ½ Street

C

6

801 Service Street

H

7

3 Hibury Street

G

8

10933 Upland Drive

A

 

 

CONTRACT COMPLETION AND COST: The Contractor, J Rivas Construction, LLC, has completed the work under the subject Contract. The project was completed within the original Contract time. The final cost of the project, including overrun and underrun of estimated unit price quantities is $4,056,333.74 an increase of $56,333.74 or 1.41% over the original Contract Amount. The increased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION:  The advertised M/WBE contract goals for this project were 13.00% MBE and 7.00% WBE. The M/W/SBE goals approved for this project were 11.00% MBE, 7.00% WBE, and 2.00% SBE. According to the Office of Business Opportunity, the actual participation achieved on this project was 4.09% MBE, 1.56% WBE, and 0.16% SBE. The MWSBE performance on this project was rated Unsatisfactory due to the following reasons: Good Faith Efforts were not achieved in meeting the MBE and WBE goals nor in the utilization goal credit subcontractors to the extent possible. Good Faith Efforts documentation was not provided to OBO when requested and the deviation process was not leveraged resulting in a non-goal credit firm performing work slated to a goal credit subcontractor. For the reasons listed, the MWSBE performance does not meet the good faith efforts requirements mandated by the City's MWSBE Program.

 

 

 

 _________________________________

Randall V. Macchi, Chief Operating Officer

Houston Public Works

 

WBS No. N-321040-0062-4

Prior Council Action:

Ordinance No. 2022-0778, dated 10-05-2022

 

 

 

 

Amount and Source of Funding:

No additional funding is required.

 

Total (original) appropriation of $4,950,000.00 from Fund No. 4040 – METRO Projects Construction DDSRF (Supported by Third Party Funds: METRO).

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Interim Chief of Staff

DO-HPW Government Relations

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Government Relations

832.395.2282

Johana Clark, Assistant Director

HPW Transportation & Drainage Operation

832.395.2274

 


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet