PULLED - This item will not be considered on Wednesday September 25

 ORDINANCE appropriating $1,376,874.75 out of Water & Sewer System Consolidated Construction Fund; approving and authorizing first amendment to Professional Engineering Services Contract between City of Houston and OMEGA ENGINEERS, INC for Work Order Engineering Services for Capacity Remedial Measures Plan for Package #2 (as approved by Ordinance No. 2021-0244) - DISTRICT I - MARTINEZ

Background:

SUBJECT: First Amendment to the Professional Engineering Services contract between the City and Omega Engineers, Inc. for Work Order Engineering Services for Capacity Remedial Measures Plan (CRMP) for Package 02.

 

RECOMMENDATION: Approve the First Amendment to the Professional Engineering Services contract with Omega Engineers, Inc. and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the CRMP for the City of Houston and is required to identify improvements necessary to address Recognized Capacity Constraints Areas (RCCAs). The work to be performed under this contract is necessary to maintain compliance with Houston's proposed wastewater consent decree with the EPA and TCEQ.  

 

DESCRIPTION/SCOPE: The project is located within the Sims Bayou North and Sims Bayou South Wastewater Treatment Plant (WWTP) Service Areas for different capacity constraint areas including but not limited to Areas 5 (Upstream of Eddington Area), 6 ( Downstream of Eddington Area), Area 7 (YMCA Area in Sims Bayou) and Area 10 (Wheeler-Telephone Road Area). The consultant shall provide services related to the CRMP, prepare engineering and technical documentation and collaborate with the City of Houston and its contractors.

 

LOCATION: The project area is in the City of Houston generally bound by Polk Street on the north, Interstate 610 on the south, Broadway Street on the east and Mykawa Rd on the west.

 

PREVIOUS HISTORY AND SCOPE: City Council approved the original contract on April 07, 2021 under Ordinance No. 2021-0244. The scope of services under the original contract consisted of evaluating the capacity of the existing Wastewater Collection and Transmission Systems (WCTS) within the study area. In addition, the scope of services included the consultant identifying improvements necessary to address RCCAs to be implemented immediately and identifying improvements in the WCTS that are hydraulically connected to the RCCAs, which would be implemented in future phases as set forth in the wastewater consent decree with the EPA and TCEQ. The scope of work under this work order contract also consisted of the consultant performing Phase I - Preliminary Engineering Services based on the cost of time and materials with a not-to-exceed agreed upon amount.

 

Under this contract, the Consultant has accomplished identification of capacity constraints areas for the Sims Bayou WWTP and Sims Bayou South Service areas and recommended resolutions that generated two (2) Houston Public Works Capital Projects for an estimated construction cost of $44 million. These projects have been submitted to the EPA for approval on schedule as per Consent Decree and transferred to Houston Public Works Capital Projects to complete design and construction phases. Houston Public Works Capital Projects has selected an Engineer of Record (EOR) for each project.

 

SCOPE OF THIS AMENDMENT AND FEE: Under the scope of this First Amendment, the Consultant will accomplish the following: Since the transfer of the previously mentioned projects to Houston Public Works Capital Projects, the need has been identified to keep the CRMP consultant until the EORs complete design phases. The CRMP consultant will be responsible to provide required communication and bridge services to all EORs and the City of Houston so that all recommended projects, as submitted to the EPA under the Consent Decree, would stay in their scope, budget and schedule.  During Phase I - Preliminary Design and Phase II – Final Design, CRMP consultant will participate with the Stakeholders, EORs, and other agencies as needed.

 

The total requested  appropriation for contract services is $1,376,874.75. 

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City Contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION: The M/WBE goal advertised for this project was 24.00%. The original contract amount totals $1,431,210.00. The Consultant has been paid $1,188,870.00 (83.07%). Of this amount, $389,025.00 (32.72%) has been paid to M/WBE sub-contractors to date. Assuming approval of the requested additional appropriation, the contract amount will increase to $2,808,084.75. The Office of Business Opportunity will continue to monitor this contract for M/WBE compliance. The Consultant proposes the following plan to meet the M/WBE goal.

 

Name of Firms

Work Description

Amount

% of Total Contract

Paid Prior M/WBE Commitment

 

$389,025.00

13.85%

Unpaid Prior M/WBE Commitment

 

$143,957.60

    5.13%

1. Red Fox Infrastructure Inc.

Computer Aided Design for Engineering projects

$357,987.44

__________

12.75%

______

 

TOTAL

$890,970.04

31.73%

 

 

 

 

 

 

 

 

 

 

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project. 

  

 

_________________________________

Randy Macchi, Chief Operating Officer

Houston Public Works

 

WBS No. R-000020-0073-3

Prior Council Action:
Ordinance No. 2021-0244, dated 04-07-2021
Amount and Source of Funding:

$1,376,874.75 - Fund No. 8500 - Water and Sewer System Consolidated Construction Fund

 

Original appropriation of $1,502,770.50 from Fund No. 8500 – Water and Sewer System Consolidated Construction Fund.

Contact Information:

Name

Service Line

Contact No.

Roberto Medina,Interim Chief of Staff

DO-HPW Government Relations

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Government Relations

832.395.2282

Akhter Hussain, Supervising Engineer

HPW Houston Water

832.395.2294


ATTACHMENTS:
DescriptionType
Signed Coversheet Signed Cover sheet
MapsBackup Material