Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 8/27/2024
District E, District I
Item Creation Date: 5/15/2024

HPW – 20FAC2445-B Change Order / Boyer, Inc.

Agenda Item#: 3.


 
                               
Summary:

RECOMMENDATION from Chief Operating Officer Houston Public Works for approval of Change Order No. 4 in the amount of $2,069,172.69 for the Lift Station Renewal and Replacement - East Ten Park, Maxey Road, Mesa Drive, Westmont, North Shore on contract with BOYER, INC - DISTRICTS E - FLICKINGER and I - MARTINEZ

This item should only be considered after passage of Item 2 above

Background:

SUBJECT: Pass a motion approving Change Order No. 4 for Lift Station Renewal and Replacement – East Ten Park, Maxey Road, Mesa Drive, Westmont, North Shore.

 

RECOMMENDATION: (SUMMARY) Pass a motion approving Change Order No. 4.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the Lift Station Renewal and Replacement Improvements program and is required to replace/upgrade lift station facilities.

 

The work to be performed under this contract award is necessary to maintain compliance with Houston wastewater consent decree with EPA and TCEQ.

 

LOCATION: 

PROJECT NAME

LOCATION

COUNCIL DISTRICT

East Ten Park Lift Station

275 Gellhorn Drive

I

Maxey Road Lift Station

909 Maxey Road

I

Mesa Drive Lift Station

3875 ½ Mesa Drive

I

Westmont Lift Station

734 Westmont Drive

E

North Shore Lift Station

13093 ½ North Shore #2 Drive

E

 

CHANGE ORDER No. (4):  This work is required for the additional work described in Change Order No. 4; a Force Main conflict with a Sanitary Sewer Line on Westmont Drive, relocation of the control panel at Westmont Lift Station, replacing the piping between the Wet Well and Valve Vault, seal leaks in the Wet Well bottom, providing spool pieces to account for the height difference at Mesa Lift Station, installing conduits, demolishing the concrete base of the existing Lift Station conflicting with the pier foundations, removing existing hatches, installing new hatches and additional paving, micro tunneling of 36-in Sanitary Sewer, Meraki MG21 procurement and the chain link fence. This scope of work is necessary to complete the execution of this project due to the inspection results. The original contract duration for this project was 500 calendar days.  The project was awarded to Boyer, Inc. with an original Contract Amount of $19,739,040.00.

The proposed Change Order No. 4 is in the amount of $2,069,172.69, or 10.48% above the original contract amount and extends the contract time by 26 days.  This will increase the original contract amount to $21,808,212.69.

 

M/WBE PARTICIPATION: The M/WBE goal established for this contract is 18.00%. The original Contract approved by Ordinance No. 2022-0423 is in the amount of $19,739,040.00.  Assuming approval of Change Order No. 4, the Contract amount will increase to $21,808,212.69.  According to the Office of Business Opportunity, the Contractor’s to date MWBE/SBE performance is 21.12%.

 

 

 

 __________________________________

Randall V, Macchi, Chief Operating Officer

Houston Public Works

           

WBS No. R-000267-0122-4

Prior Council Action:

Ordinance No. 2022-0423, dated 06-01-2022

Amount and Source of Funding:

No additional funding is required.

 

 

 

Original (previous) appropriation of $21,862,944.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund.

Subsequent additional appropriation of $2,247,631.32 - Fund No. 8500 – Water and Sewer System Consolidated Construction.

 

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Interim Chief of Staff 

DO-HPW Government Relations

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Government Relations

832.395.2282

Markos Mengesha, Assistant Director

FAC- HPW Capital Projects

832.395.2365

 
ATTACHMENTS:
DescriptionType
Signed Coversheet Signed Cover sheet