Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/5/2023
District A, District B, District G, District H, District I
Item Creation Date: 11/1/2023

HPW – 20WWO1127 Accept Work / PM Construction & Rehab, LLC dba IPR South Central

Agenda Item#: 18.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $5,169,264.48 and acceptance of work on contract with PM CONSTRUCTION & REHAB, LLC dba IPR SOUTH CENTRAL for Wastewater Collection System Rehabilitation and Renewal - 3.57% under the original contract amount (4235-111) - DISTRICTS A - PECK; B - JACKSON; G - HUFFMAN; H - CISNEROS and I - GALLEGOS

Background:

SUBJECT: Accept Work for Wastewater Collection System Rehabilitation and Renewal.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final contract amount of $5,169,264.48 or 3.57% under the original contract amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the Neighborhood Sewer Rehabilitation Program required to renew/replace various deteriorated neighborhood collection systems throughout the City. The project involved wastewater collection system rehabilitation and renewal. The purpose was to reduce sanitary sewer overflows, which was accomplished by renewal/rehabilitation of deteriorated collection systems.

 

DESCRIPTION/SCOPE: This project consisted of wastewater collection system rehabilitation and renewal. The project was awarded to PM Construction & Rehab, LLC dba IPR South Central, with 730 calendar days allowed for construction and an original contract amount of $5,360,612.84.

 

LOCATION: The projects are located throughout the City of Houston.

 

CONTRACT COMPLETION AND COST: The contractor, PM Construction & Rehab, LLC dba IPR South Central, has completed the work under the subject contract. The project was completed beyond the established completion date with an additional 90 days approved by Change Order No. 2. The final cost of the project, including overrun and underrun of estimated unit price quantities is $5,169,264.48, a decrease of $191,348.36 or 3.57% under the original contract amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised M/WBE contract goals for the project were 19.44% MBE and 9.17% WBE (28.61% total). The M/WBE goals approved for this project were 19.44% MBE and 9.17% WBE (28.61% total). According to the Office of Business Opportunity, the actual participation achieved on this project was 19.75% MBE and 8.46% WBE (28.21% total). The standard for meeting MWSBE participation goals is the demonstration of Good Faith Efforts. The Contractor’s M/WBE performance on this project was rated Satisfactory for the following reasons: The Prime exceeded the MBE goal, was less than one percent of achieving their WBE goal, and made GFE to utilize all goal credit subcontractors for this project. For the reasons listed, the Contractor’s performance met our expectations and meets the intent and spirit of the City’s MWSBE program.

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. R-000266-0289-4

File No. 4235-111

Prior Council Action:

Ordinance No. 2019-0466, dated 06-19-2019

Amount and Source of Funding:

No additional funding required.

 

Original appropriation of $5,703,643.00 from Fund No. 8500 – Water and Sewer System Consolidated Construction Fund. This project was eligible for low interest funding through a State Revolving Fund (SRF) Equivalency loan. 

 

 

 

 

Contact Information:

Greg Eyerly

Senior Assistant Director, Houston Water

Phone: (832) 395-4979

ATTACHMENTS:
DescriptionType
Signed Coversheet Signed Cover sheet
Council District MapBackup Material
Location ListBackup Material