Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/17/2023
District G
Item Creation Date: 10/5/2023

25CONS559 – Accept Work – Gadberry Construction Company, Inc. – Kendall Neighborhood Library and Community Center Restoration (Harvey)

Agenda Item#: 5.


 
                               
Summary:

RECOMMENDATION from Director General Services Department for approval of final contract amount of $4,553,351.25 and acceptance of work on contract with GADBERRY CONSTRUCTION COMPANY, INC for the Kendall Neighborhood Library and Community Center Restoration (Harvey) Project - 10.06% over the original contract amount and under the approved 16% contingency - DISTRICT G - HUFFMAN

Background:

RECOMMENDATION: The General Services Department recommends approval of the final contract amount of $4,553,351.25 and acceptance of work on the construction contract with Gadberry Construction Company, Inc., for the Kendall Neighborhood Library and Community Center Restoration (Harvey) project - 10.06% over the original construction amount and under the approved 16% contingency.

 

PROJECT LOCATION:  609 N Eldridge Pkwy, Houston, TX 77079

 

PROJECT DESCRIPTION:  The project restored the Kendall Neighborhood Library and Community Center to pre-Hurricane Harvey conditions. The project restored and encased the electrical equipment to prevent damage from future storms, repaired building windows and roof parapet to prevent water penetration; installed new flood doors; relocated the existing storm pipe; installed new data cables and security cameras; updated the elevator system and the restroom facilities and purchased and installed new library furniture and equipment.

 

CONTRACT COMPLETION AND COST: The contractor completed the project within 508 days: the original contract time of 200 days, plus 37 days approved by Change Orders and 271 days of overrun days caused by supply chain issues and electrical service entrance relocation. The final cost of the project, including Change Orders, is $4,553,351.25, an increase of $416,351.25 over the original contract amount.

 

PREVIOUS CHANGE ORDERS:  Change Order No.1-9 included additional general condition cost, additional excavation required by soil condition, and modifications to the exterior paving system; added substrate structural support for the new metal panel system, upgraded electrical service entrance, security system, and fixed misc. damaged building system components that were not identified before the construction.   

 

M/WBE PARTICIPATION:  The advertised M/WBE contract goals for this project were 19% MBE and 11% WBE (30% total). The M/WBE goals approved for this project were 19.65% MBE and 11% WBE (30.65% total). According to the Office of Business Opportunity, the actual participation achieved on this project was 23.17% MBE and 0% WBE (23.17% total). The standard for meeting MWBE participation goals is the demonstration of Good Faith Efforts. Gadberry Construction Company, Inc.’s M/WBE performance on this project was rated Satisfactory due to Good Faith Efforts for the following reasons: Gadberry Construction, Inc. exceeded the MBE goal and made good faith efforts to achieve the WBE goal and utilized all goal credit subcontractors. For the reasons listed, Gadberry Construction Company, Inc.’s performance meets the intent and spirit of the City of Houston’s MWSBE program.

 

WBS No: D-HARVEY-1073-4

 

Prior Council Action:

Ordinance No. 2021-319, dated April 28, 2021

Ordinance No. 2022-908, dated November 30, 2022

 

WBS No: D-HARVEY-1073-4

 

DIRECTOR’S SIGNATURE/DATE:

 

 

__________________________

C. J. Messiah, Jr.

General Services Department

 

 

 

____________________________

Rhea Brown Lawson, Ph.D.

Houston Public Library

 

 

____________________________

Kenneth Allen

Houston Parks and Recreation Department

 

Prior Council Action:

Ordinance No. 2021-319, dated April 28, 2021

Ordinance No. 2022-908, dated November 30, 2022

Amount and Source of Funding:

No Additional Funding Required

 

Previous Funding

$4,971,317.50     Miscellaneous Capital Projects/Acquisitions CP Series E (4039)

Contact Information:

Enid M. Howard

Council Liaison       

Phone:  832.393.8023

ATTACHMENTS:
DescriptionType
Signed Coversheet Signed Cover sheet
25CONS559 - MapsBackup Material