Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/19/2023
District D
Item Creation Date: 8/4/2023

HPW – 20FDL2309 Contract Award / Main Lane Industries Ltd.

Agenda Item#: 32.


 
                               
Summary:

ORDINANCE appropriating $22,840,400.00 out of Water & Sewer System Consolidated Construction Fund, awarding contract to MAIN LANE INDUSTRIES LTD for Force Main Flow Diversion from Sagemont Lift Station to Southeast WWTP; setting a deadline for the bidder's execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for CIP Cost Recovery, contingency, construction management, and testing services relating to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund - DISTRICT D - EVANS-SHABAZZ

Background:

SUBJECT: Contract Award for Force Main Flow Diversion from Sagemont Lift Station to Southeast Wastewater Treatment Plant (WWTP).

 

RECOMMENDATION:  Award a Construction Contract to Main Lane Industries Ltd. for Force Main Flow Diversion from Sagemont Lift Station to Southeast Wastewater Treatment Plant (WWTP) and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION:  This project is part of the City’s Capital Improvement Plan (CIP) Consolidation Package for wastewater facilities and is required to control operations and maintenance cost and ensure regulatory compliance.

 

The work to be performed under this contract award is necessary to maintain compliance with Houston's wastewater consent decree with EPA and TCEQ.

 

DESCRIPTION/SCOPE:  This project consists of the construction of a 36-inch force main by combination of open cut and trenchless construction methods, including installation of valves, connections and appurtenances. The Contract duration for this project is 540 calendar days. This project was designed by HDR Engineering Inc.

 

LOCATION: The project area is generally bound by Fuqua Street on the north, Beamer Ditch on the south, Sageville Drive on the east and Kingspoint Road on the west. 

 

BIDS: This project was advertised for bidding on May 26, 2023. Bids were received on June 22, 2023.  The Three (3) bids are as follows:

 

 

Bidder

Bid Amount

 

1.

Main Lane Industries, Ltd.

$20,163,821.00

 

2.

Reytec Construction

$21,239,425.00

 

3.

Harper Brothers Construction

$22,033,428.50

 

 

AWARD: It is recommended that this construction contract be awarded to Main Lane Industries Ltd. with a low bid of $20,163,821.00 and Addenda Numbers 1 and 2 be made a part of this Contract.

 

PROJECT COST: The total cost of this project is $22,840,400.00 to be appropriated as follows:

 

· Bid Amount

$ 20,163,821.00

· Contingencies

$   1,008,206.50

· Testing Services

$      100,000.00

· CIP Cost Recovery

$   1,008,206.50

· Construction Management

$      560,166.00

 

 

Testing Services will be provided by Paradigm Consultants, Inc. under a previously approved contract.

 

Construction Management Services will be provided by Sowells Consulting Engineers, LLC under a previously approved contract.

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case company Main Lane Industries Ltd. is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

 

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 13.00% MBE goal and 7.00% WBE goal for this project.

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

Texas Concrete Enterprise Ready Mix, Inc.

Concrete Manufacture

$   604,914.63

  3.00%

2.

Castec Construction LLC

Concrete Paving & Driveways

$1,209,829.26

  6.00%

3.

C.M. Nunez Trucking Co.

Dump Trucking

$   604,914.63

  3.00%

4.

T. Gray Utility & Rehab Co., LLC.

Water and Sewer Construction

$   201,638.21

  1.00%

 

 

TOTAL

$2,621,296.73

13.00%

 

 

WBE - Name of Firms

Work Description

Amount

% of Contract

1.

Access Data Supply, Inc.

Pipe Material

$1,411,467.47

  7.00%

 

 

TOTAL

$1,411,467,47

7.00%

 

 

FISCAL NOTE:  No significant Fiscal Operating impact is anticipated as a result of this project.

 

All known rights-of-way, easements and/or right-of-entry required for the project have been acquired.

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. R-000536-0033-4

Amount and Source of Funding:

$22,840,400.00- Fund No. 8500 – Water and Sewer System Consolidated Construction

Contact Information:

Markos E. Mengesha P.E., CCM

Assistant Director, Capital Projects

Phone: (832) 395-2365

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
Maps Backup Material