Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/12/2023
District G, District J
Item Creation Date: 4/20/2023

HPW - 20MEM59 / Accept Work / BRH-Garver Construction, L.P.

Agenda Item#: 5.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $26,781,754.34 and acceptance of work on contract with BRH-GARVER CONSTRUCTION L.P., for Fountain View Regional Lift Station Construction and Abandonment of Westheimer No. 1 Lift Station - 5.00% over the original Contract Amount - DISTRICTS G - HUFFMAN and J - POLLARD

Background:

SUBJECT:  Accept Work for Fountain View Regional Lift Station Construction and Abandonment of Westheimer No.1 Lift Station.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $26,781,754.34 or 5.00% over the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City`s Capital Improvement Plan (CIP) for wastewater facilities program and was required to comply with Houston`s proposed wastewater consent decree with EPA and TCEQ.

 

DESCRIPTION/SCOPE: This project consisted of the construction of a new Fountain View Regional Lift Station, demolition of the existing Westheimer No. 1 Lift Station of approximately 4,500 linear feet of 36-inch diameter force main and approximately 4,600 linear feet of 48-inch diameter gravity sanitary sewer. The new lift station included furnishing and installing mechanical and electrical equipment. Amani Engineering, Inc. designed the project with 630 calendar days allowed for construction. The project was awarded to BRH-Garver Construction, L.P. with an original Contract Amount of $25,506,517.00.

 

LOCATION:

  

PROJECT NAME

LOCATION

COUNCIL DISTRICT

Westheimer No. 1 Lift Station 

5882 Westheimer Road

G

Fountain View Lift Station 

3434 Fountain View Drive

J

 

CONTRACT COMPLETION AND COST: The Contractor, BRH-Garver Construction, L.P., has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 269 days approved by Change Order Nos. 2,6,10,12,15, and 16. The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos.1,3,4,5,and 7-16 is $26,781,754.34, an increase of $1,275,237.34 or 5.00% over the original Contract Amount. The increased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION:  The advertised M/WBE contract goals for this project were 13.00% MBE and 7.00% WBE (20.00 % total). The M/W/SBE goals approved for this project were 13.06% MBE, 4.79% WBE and 2.46% SBE (20.31% total). According to the Office of Business Opportunity, the actual participation achieved on this project was 15.17% MBE, 6.13% WBE, and 2.05% SBE (23.35% total). The standard for meeting MWSBE participation goals is the demonstration of Good Faith Efforts. The Contractor’s M/W/SBE performance on this project was rated Satisfactory for the following reasons: The Prime exceeded the MBE goal by 2.11% and WBE goal by 1.34% and came within less than 1.00% of meeting the SBE goal. Apart from three (3) subs, the Prime was able to utilize all remaining goal credit subcontractors on this project.  For the reasons listed, the Contractor's performance met expectations and meets the intent and the spirit of the City's MWSBE program.

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No(s). R-0000536-0023-4

Prior Council Action:

Ordinance No. 2020-0287, dated 04-01-2020

Amount and Source of Funding:
No additional funding required.

Total (original) appropriation of $30,413,495.00 from Fund No. 8500 – Water and Sewer System Consolidated Construction
Contact Information:
Markos E. Mengesha P.E., CCM 
Assistant Director, Capital Projects 
Phone: (832) 395-2365 
 
ATTACHMENTS:
DescriptionType
Maps Backup Material
Signed CoversheetSigned Cover sheet