CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/13/2022
District B
Item Creation Date: 7/5/2022

HPW – 20NHK13-A Addtn’l Approp / Fused Industries, LLC

Agenda Item#: 3.


 
                               
Summary:

ORDINANCE appropriating the sum of $433,605.76 out of Dedicated Drainage and Street Renewal Capital Fund as an additional appropriation to a contract between the City of Houston and FUSED INDUSTRIES, LLC for the Laura Koppe Road Paving and Drainage Project from Hirsch Road to Homestead Road for Change Order Nos. 2, and 6 through 12 (approved by Ordinance No. 2019-0653); providing funding for CIP cost recovery to construction of facilities financed by the Dedicated Drainage and Street Renewal Capital Fund - DISTRICT B - JACKSON

Background:

SUBJECT: Adopt an Ordinance approving an Additional Appropriation for Change Order Nos. 2, and 6 through 12 for Laura Koppe Road Paving & Drainage from Hirsch to Homestead.

 

 RECOMMENDATION: (SUMMARY) Adopt an Ordinance approving an Additional Appropriation of $433,605.76 for Laura Koppe Road Paving & Drainage from Hirsch to Homestead.

 

 PROJECT NOTICE/JUSTIFICATION: This project is part of the Street and Traffic Capital Improvement Plan and is required to improve traffic circulation, mobility, and drainage in the service area and to meet City of Houston’s design standards. These improvements will upgrade the existing roadway to Major Thoroughfare Freeway Plan (MTFP) standards.

 

 DESCRIPTION/SCOPE: The project consists of 49,600 square yards of 9-inch reinforced concrete pavement with 6-inch curb spanning Laura Koppe Road from Hirsch Road to Homestead Road. It also consists of 6,000 linear feet of 16-inch water line improvements, 7,900 linear feet of reinforced concrete pipe storm sewer, and 8,000 linear feet of reinforced concrete box storm sewers. The Project was awarded to Fused Industries, LLC with an original Contract Amount of $15,554,200.00.

 

 LOCATION: The project area is generally bound by Firnat Street on the north, Weaver Road on the south, Homestead Road on the east, and Hirsch Road on the west.

 

 ADDITIONAL APPROPRIATION:  An approval is requested for an additional appropriation of $412,957.87 in excess of the original contract value and an extension of 29 days of contract time for additional work described in Change Orders Nos. 2, and 6 through 12. This scope of work is necessary to complete the execution of this project due to the inspection results. The requested appropriation will cover payment for additional work completed by the Contractor as authorized in the Change Orders listed below.

 

The total requested appropriation is $433,605.76 to be appropriated as follows: $412,957.87 for contract services and $20,647.89 for CIP Cost Recovery.

 

Change Order No.

Amount

Days

Description of Work

2

$      41,700.00

0

8” water line offset

6

$     153,080.28

14

Remove/Dispose of existing 16” water line, downtime due to existing water line conflicts, and furnish and install temporary siphon

7

$      61,775.00

0

Pumping due to water backing up from HCFCD silted channels and sawcut 9” concrete pavement

8

$      14,800.00

0

Additional traffic control signs

9

$      55,555.00

0

Furnish 32" sanitary MH Ring and cover, and re-grading Hirsh Rd. to adjust for positive drainage and accommodate the driveway

10

$      27,019.93

0

Remove and dispose existing 8-inch and 6-inch waterline and additional CenterPoint Energy conduit for proposed street lights

11

$      21,498.75

0

Furnish and install retaining curb

12

$      37, 528.91

15

Dewatering and cleaning of storm manholes,

TOTAL

$     412,957.87

29

 

 

 HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case, Fused Industries, LLC is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

 PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides benefits for some employees but will pay into the Contractor Responsibility Fund for others, in compliance with City policy.

 

 

 

 

 

 

 M/WBE PARTICIPATION: The M/WBE goal established for this contract is 18.01%.  The original Contract is in the amount of $15,554,200.00.  Assuming approval of Change Order Nos. 2, and 6  through 12, the Contract amount will increase to $15,967,157.87. According to the Office of Business Opportunity verification, the Contractor’s to-date MWBE/SBE performance is 17.07%.

 

 FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

___________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

           

WBS Nos. N-000813-0001-4, R-000500-0184-4, S-000500-0184-4

Prior Council Action:

Ordinance No. 2019-0653, dated 08-21-2019

 

 

 

Amount and Source of Funding:

$433,605.76 - Fund No. 4042 - Dedicated Drainage and Street Renewal Capital Fund – Drainage Charge

 

Original (previous) total appropriation $19,107,330.00.

$16,766,900.12 from Fund No. 4042 – Street & Traffic Control and Storm Drainage DDSRF (Supported by Drainage Utility Charge) and $2,340,429.88 from Fund No. 8500 - Water and Sewer System Consolidated Construction

Contact Information:

Juan Chavira, P.E., PMP, CEM

Assistant Director, Capital Projects

Houston Public Works