Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/4/2022
ALL
Item Creation Date: 5/23/2022

HPW - 20DWO78 Accept Work/T Construction, LLC

Agenda Item#: 7.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $1,775,894.12 and acceptance of work on contract with T CONSTRUCTION, LLC for Small and Large Diameter Waterline Valve Replacement Project - 0.68% over the original contract amount and under the 5% contingency amount (WA11269)

Background:

SUBJECT: Accept Work for Small and Large Diameter Waterline Valve Replacement Project.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final contract amount of $1,775,894.12 or 0.68% over the original contract amount, accept the work, and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project provided for the removal, disposal and installation of new small and large diameter waterline valves and ancillary work.    

 

DESCRIPTION/SCOPE: This project consisted of the replacement of small and large diameter waterline valves that were deteriorated beyond repair, the installation of new valves, and the replacement of some small and large diameter water lines that are associated with the installation of the new valves. The project was awarded to T Construction, LLC with an original Contract Amount of $1,763,875.40. The contract duration for this project was 365 calendar days. 

 

LOCATION: The projects are located throughout the City of Houston. 

 

CONTRACT COMPLETION AND COST: The contractor, T Construction, LLC has completed the work under the subject contract. The project was completed within the original contract time. The final cost of the project, including overrun and underrun of estimated unit price quantities and previous Change Order No. 1 is $1,775,894.12, an increase of $12,018.72 or 0.68% over the original Contract Amount and under the 5% contingency amount. The increased cost is the result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised M/WBE contract goals for this project were 12% MBE and 7% WBE (19% total). The M/W/SBE goals approved for this project were 12% MBE and 7% WBE (19% total). According to the Office of Business Opportunity, the actual participation achieved on this project was 22.38% MBE and 2.74% WBE (25.12% total). The standard for meeting MWSBE participation goals is the demonstration of Good Faith Efforts. The Contractor's M/W/SBE performance on this project was rated Satisfactory for the following reasons: Although the Prime experienced a shortfall with WBE participation due to the limited work orders requiring trucking services, the Prime was successful in exceeding the MBE goal by 10.38%. In addition, the Prime made good faith efforts to utilize all goal credit subcontractors to capacity on this project. For the reasons listed, the Contractor's performance meets the intent and spirit of the City's MWSBE program.

 

 

_______________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. S-000702-0013-4; File No. WA 11269

 

Prior Council Action:

Ordinance No. 2017-0883, dated 11-15-2017

 

Amount and Source of Funding:

No additional funding required

 

Original appropriation of $1,917,069.17 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund.

Contact Information:

Andrew Molly, P.E.

Senior Assistant Director, DWO

Houston Public Works Department

Phone (832) 395-3785

 

 

 

 

 

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material