Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/15/2024
District A, District B, District C, District D, District G, District H, District I, District K
Item Creation Date: 12/20/2021

HPW - 20WWO1018 Accept Work/RedZone Robotics, Inc.

Agenda Item#: 5.


 
                               
Summary:

RECOMMENDATION from Chief Operating Officer, Houston Public Works for approval of final contract amount of $1,915,407.15 and acceptance of work on contract with REDZONE ROBOTICS, INC for Large Diameter Sanitary Sewer Inspection Using Robotic Technology - 2.12% over the original contract amount (4277-102) - DISTRICTS A - PECK; B - JACKSON; C - KAMIN; D - EVANS-SHABAZZ; G - HUFFMAN; H - CASTILLO; I - MARTINEZ and K - CASTEX-TATUM

Background:

SUBJECT: Accept Work for Large Diameter Sanitary Sewer Inspection Using Robotic Technology.

 

RECOMMENDATION: (Summary) Pass a motion to approve the final contract amount of $1,915,407.15, which is 2.12% over the original contract amount and under the 5% contingency amount, accept the work, and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATIONThis project was part of the Neighborhood Sewer Rehabilitation Program and was required to renew/replace various deteriorated neighborhood collection systems throughout the City. The project involved large diameter sanitary sewer inspection using robotic technology.   The purpose was to reduce the sanitary sewer overflows, which was accomplished by cleaning of the sewer lines and robotic inspection to identify sewer lines in need of rehabilitation/renewal.    

 

DESCRIPTION/SCOPE: This project consisted of large diameter sanitary sewer inspection using robotic technology. The project was awarded to RedZone Robotics, Inc., with an original contract amount of $1,875,575.00. The Contract duration for this project was 730 calendar days.

 

LOCATION: The projects are located throughout the City of Houston within Council Districts A, B, C, D, G, H, I and K.

 

CONTRACT COMPLETION AND COST: The contractor, RedZone Robotics, Inc., has completed the work under the subject contract. The contract was completed beyond the established completion date with an additional 90 days approved by Change Order No. 1. The final cost of the project, including overrun and underrun of estimated unit price quantities, is $1,915,407.15, an increase of $39,832.15 or 2.12% over the original contract amount. The increased cost is a result of the difference between planned and measured quantities.   

 

MWDBE PARTICIPATION: The advertised M/WBE contract goals for this project were 8.65% MBE and 3.65% WBE (12.30% total). The M/W/SBE goals approved for this project were 9% MBE and 4% SBE (13% total). According to the Office of Business Opportunity, the actual participation achieved on this project was 3.07% MBE and 0.76% SBE (3.83% total). The standard for meeting MWSBE participation goals is the demonstration of Good Faith Efforts. The Contractor’s M/W/SBE performance on this project was rated Unsatisfactory for the following reasons: The Prime’s MBE goal attainment fell short of the goal by more than 5.00% and WBE participation fell short of the goal by approximately 3.00% - an overall MWBE participation shortfall of approximately 8.50%. The Prime failed to make good faith efforts to engage additional goal credit subcontractors to perform sanitary sewer cleaning and television work when there was ample opportunity to do so. Engaging additional certified firms to participate on the project could have increased the Prime’s overall MWBE goal attainment on the project. For the reasons listed, the Contractor’s performance does not meet the intent and the spirit of the City of Houston’s MWSBE Program.

 

 

 

__________________________________

Randall V. Macchi, Chief Operating Officer

Houston Public Works

 

WBS No. R-002013-0053-4, File No. 4277-102

Prior Council Action:

Ordinance No. 2018-0398 dated 05-16-2018

Amount and Source of Funding:

No additional funding required.

 

Original appropriation of $1,969,354.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund

 

 

 

 

 

Contact Information:

Name

Service Line

Contact Number

Roberto Medina, Interim Chief of Staff

DO-HPW Government Relations

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Government Relations

832.395.2282

Dr. Joseph G. Majdalani, P.E.Senior Assistant Director

Houston Water

832.395.8530


ATTACHMENTS:
DescriptionType
Council District MapBackup Material
Location ListBackup Material
Signed Coversheet Backup Material