Summary:

ORDINANCE approving and authorizing first amendment to Professional Engineering Services Contract between City of Houston and JONES & CARTER, INC for 48-Inch Water Line from SH 288 to Cullen Boulevard along East Orem Drive (Approved by Ordinance No. 2021-0782) - DISTRICT D - EVANS-SHABAZZ

Background:

SUBJECT: First Amendment to Professional Engineering Services Contract between the City and Jones & Carter, Inc., for 48-Inch Water Line from SH 288 to Cullen Boulevard along East Orem Drive.

 

RECOMMENDATION: Approve First Amendment to the Professional Engineering Services Contract with Jones & Carter, Inc.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the design and construction of transmission and distribution lines to convey treated water.

 

DESCRIPTION/SCOPE: This project consists of design and construction of approximately 10,000 linear feet of 48-Inch Water Line from Cullen Boulevard to State Highway 288.

 

LOCATION: The project area is located along East Orem Drive from State Highway 288 to Cullen Boulevard

 

PREVIOUS HISTORY AND SCOPE:  City Council approved the original Contract on September 8, 2021 under Ordinance No. 2021-0782. The scope of services under the Original Contract consisted of Phase I - Preliminary Design, Phase II – Final Design, Phase III - Construction Phase Services and Additional Services.

 

SCOPE OF THIS AMENDMENT: Under the scope of this First Amendment, the original Exhibit A-1 that was included in the contract at the time of council award will be replaced in its entirety with the most current version. The Exhibit A-1 serves as an added exhibit to the contract which outlines detailed scope of work that is not included in the standard Professional Engineering Services Contract.

 

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. S-000900-0173-3

Prior Council Action:

Ordinance No. 2021-0782 dated 09-08-2021

Amount and Source of Funding:

No additional funding required.

 

Original (previous) appropriation of $2,310,000.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction.

Contact Information:

R. Jeff Masek, P.E., CCM

Assistant Director, Capital Projects

Phone: (832) 395-2387