SUBJECT: Contract Award for FY2022 Local Drainage Program (LDP) Contract #3.
RECOMMENDATION: (SUMMARY) Award a Construction Contract to PM Construction & Rehab, LLC dba IPR South Central for FY2022 Local Drainage Program (LDP) Contract #3 and appropriate funds.
PROJECT NOTICE/JUSTIFICATION: This project is part of the Transportation and Drainage Operations Program and will provide work authorization on a location by location as needed basis, to preserve, repair, rehabilitate or reconstruct the storm water drainage asset along with street rehabilitation to such a condition that may be effectively used for its designated functional purpose.
DESCRIPTION/SCOPE: This Citywide program provides construction services to resolve localized storm water drainage problems. The scope is established by each work authorization. The contract duration for this project is 730 calendar days.
LOCATION: The projects are located throughout the City of Houston.
BIDS: This project was advertised for bidding on July 30, 2021. Bids were received on August 19, 2021. The eight (8) bids are as follows:
|
|
Bidder
|
Adjustment Factor
|
|
|
1.
|
PM Construction & Rehab, LLC dba IPR South Central.
|
0.719
|
|
2.
|
Grava, LLC.
|
0.750
|
|
3.
|
T Construction, LLC.
|
0.752
|
|
4.
|
Nerie Construction.
|
0.766
|
|
5.
|
DL Glover Inc.
|
0.769
|
|
6.
|
RAC Industries.
|
0.910
|
|
7.
|
Total Contracting Limited.
|
1.000
|
|
8.
|
J. Rivas Construction LLC.
|
1.120
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AWARD: It is recommended that this construction contract be awarded to PM Construction & Rehab, LLC dba IPR South Central with a low bid of $5,000,000.00 (0.719 Adjustment Factor).
PROJECT COST: The total cost of this project is $5,750,000.00 to be appropriated as follows:
|
· Bid Amount
|
$5,000,000.00
|
|
· Contingencies
· CIP Cost Recovery
|
$250,000.00
$250,000.00
|
|
· Testing Services
|
$250,000.00
|
Testing Services will be provided by Terracon Consultants, Inc. under a previously approved contract.
HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case PM Construction & Rehab, LLC dba IPR South Central is a designated HHF company, but they were the successful awardee without application of the HHF preference.
PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the contractor provides health benefits to eligible employees in compliance with City policy.
M/WBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 7% MBE goal and 2% WBE goal for this project.
|
MBE - Name of Firms
|
Work Description
|
Amount
|
% of Contract
|
|
|
|
|
|
|
|
1.
|
C&A Construction, LLC
|
Underground Construction Including Sewer Line
|
$350,000.00
|
7.00%
|
|
|
|
|
|
|
|
|
|
TOTAL:
|
$350,000.00
|
7.00%
|
|
|
WBE - Name of Firms
|
|
|
|
|
2.
|
BUKU Contractor's Supply, LLC
|
Construction Supplies
|
$100,000.00
|
2.00%
|
|
|
TOTAL:
|
$100,000.00
|
2.00%
|
|
|
|
|
|
|
|
|
CONTRACT TOTAL
|
$450,000.00
|
9.00%
|
FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.
_________________________________
Carol Ellinger Haddock, P.E.
Director
Houston Public Works
WBS No. M-420126-0120-4
|