Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/28/2021
District H, District J
Item Creation Date:

HPW-20PMO50 Accept Work JFT Construction, Inc

Agenda Item#: 1.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $6,037,222.32 and acceptance of work on contract with JFT CONSTRUCTION, INC for FY2019 Pavement Repair & Rehab Work Orders #1 - 0.62% over the original contract amount and under 5% contingency amount - DISTRICTS H - CISNEROS and J - POLLARD

Background:

SUBJECT:  Accept Work for FY2019 Pavement Repair & Rehab Work Orders #1

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $6,037,222.32 or 0.62% over the original Contract Amount, accept the Work and authorize final payment.

PROJECT NOTICE/JUSTIFICATION: This project was part of the City Wide Panel Replacement program and was required to improve and maintain a safe road surface and accessibility.

DESCRIPTION/SCOPE: This project consisted of the resurfacing of arterial and major thoroughfare streets with concrete panel replacement along with the repair and improvements to curbs and accessible ramps. The project involved the design and construction of concrete panels, base repair and pavement markings as needed. The project was designed in-house with 730 calendar days allowed for construction. The project was awarded to JFT Construction, Inc. with an original Contract Amount of $6,000,000.00.

LOCATION: The project was located in three locations.

 

Street From To Council District
 Memorial Bagby Shepherd H
 Memorial Shepherd Westcott H
 S. Gessner  (S) US 59 Hwy Bissonnet J


CONTRACT COMPLETION AND COST: The Contractor, JFT Construction, Inc., has completed the work under the subject Contract. The project was completed on time. The final cost of the project, including overrun and underrun of estimated unit price quantities, and Change Orders 1 and 2 is $6,037,222.32, an increase of $37,222.32 or 0.62% over the original Contract Amount and under 5% contingency amount. The increased cost is a result of the difference between planned and measured quantities.

M/WSBE PARTICIPATION: The advertised M/WBE contract goals for this project were 11.00% MBE and 7.00% WBE (18.00% total). The M/W/SBE goals approved for this project were 11.00% MBE, 7.00% WBE, and 0.00% SBE (18.00% total). According to the Office of Business Opportunity, the actual participation achieved on this project was 22.16% MBE, 10.67% WBE, and 0.00% SBE (32.83% total). The standard for meeting MWSBE participation goals is the demonstration of Good Faith Efforts. The Contractor’s M/W/SBE performance on this project was rated Outstanding for the following reasons: Prime utilized all goal credit subcontractors and exceeded the MBE and WBE participation goals by more than 1.00%. For the reasons listed, the Contractor’s performance exceeded our expectations and meets the intent and the spirit of the City’s MWSBE program.



_________________________________
Carol Ellinger Haddock, P.E., Director
Houston Public Works

WBS No(s). N-321040-0009-4


Prior Council Action:
Ordinance No. 2019-0420, dated 06/05/2019
Amount and Source of Funding:

No additional funding required.

Total (original) appropriation of $7,200,000.00 from Fund 4042 – Street & Traffic Control and Storm Drainage DDSRF (Supported by Ad Valorem Tax).

 

 


Contact Information:
Michael Wahl, PE, PTOE
Transportation and Drainage Operations
Phone: (832) 395-2443