Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 11/2/2021
District B, District E
Item Creation Date: 8/27/2021

HPW – 20PK24 Accept Work / Harper Brothers Construction, LLC

Agenda Item#: 9.


 
                               
Summary:

RECOMMENDATION from Director of Houston Public Works for approval of final contract amount of $27,840,979.24 and acceptance of work on contract with HARPER BROTHERS CONSTRUCTION, LLC for 108-inch Waterline along City Easements from Union Pacific Railroad to John Ralston Road - 1.69% under the original contract amount - DISTRICTS B - JACKSON and E - MARTIN

Background:

SUBJECT:  Accept Work for 108-inch Waterline along City Easements from Union Pacific Railroad to John Ralston Road.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $27,840,979.24 or 1.69% under the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION:  This project was part of the City’s Surface Water Transmission program and supported the execution of the Northeast Transmission line projects from the Northeast Water Purification Plant to the Water Authorities take-points for the Infrastructure Capital Improvement Plan.  It was required to improve existing water distribution systems and to meet Harris-Galveston Coastal Subsidence District’s Legislative mandate to regulate the withdrawal of groundwater.  The project was a combination of water line construction, public utility adjustments and roadway pavement replacement.

 

DESCRIPTION/SCOPE: This project consisted of the construction of approximately 7,800 linear feet of a 108-inch and 130 linear feet of a 24-inch transmission water line, and along with associated adjustments to storm sewer, and roadway pavement.  Aurora Technical Services, LLC and Lockwood, Andrews & Newnam designed the project with 570 calendar days allowed for construction. The project was awarded to Harper Brothers Construction, LLC with an original Contract Amount of $28,318,720.05.

 

LOCATION: The project area is along North Sam Houston Parkway East and City easements from East of Union Pacific Railroad to John Ralston Road.  

 

CONTRACT COMPLETION AND COST: The Contractor, Harper Brothers Construction, LLC., has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 15 days approved by Change Order Nos. 2, 4, 5, and 6. The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos. 2, 3 and 5 is  $27,840,979.24, a decrease of $477,740.81 or 1.69% under the original Contract Amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised M/WSBE contract goals for this project were 12.00% MBE and 7.00% WBE (19.00% total). The M/W/SBE goals approved for this project were 10.75% MBE, 5.11% WBE, and 3.16% SBE (19.02% total). According to the Office of Business Opportunity, the actual participation achieved on this project was 8.91% MBE, 5.61% WBE, and 1.43% SBE (15.95% total). The standard for meeting MWSBE participation goals is the demonstration of Good Faith Efforts. The Contractor’s M/W/SBE performance on this project was rated Satisfactory Due to Good Faith Efforts for the following reasons: The Prime exceeded the WBE goal on the contract. Although the Prime failed to meet the MBE and SBE goal, they made good faith efforts to utilize all listed MWSBE goal credit subcontractors to full capacity. For the reasons listed, the contractor's performance meets the intent and the spirit of the City of Houston's MWBE program.

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. S-000900-0154-4

Prior Council Action:

Ordinance No. 2019-0236, dated 04-03-2019

Ordinance No. 2020-0088, dated 01-29-2020

Amount and Source of Funding:

No additional funding required. 

 

Total (original) appropriation of $32,152,500.00

 

$1,114,209.84 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund

$17,794,251.75 from Fund No. 8507 - Water Authorities Capital Contribution-NETL Fund

$13,244,038.41 transfer from Fund No. 8426- NETL Expansion- SWIFT into Fund No. 8508 - HPW -NETL Construction Fund and Appropriate from Fund No. 8508 - HPW-NETL Construction Fund

$13,230.09 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund

 

 

Contact Information:

R. Jeff Masek, P.E., CCM

Assistant Director, Capital Projects

Phone: (832) 395-2387

ATTACHMENTS:
DescriptionType
Coversheet (revised)Signed Cover sheet
MapsBackup Material