Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 8/31/2021
District C
Item Creation Date: 7/29/2021

25PARK375 - Accept Work RCA - Avondale Promenade Park - Landscape Art, Inc.

Agenda Item#: 9.


 
                               
Summary:

RECOMMENDATION from Director General Services Department for approval of final contract amount of $904,385.00 and acceptance of work on contract with LANDSCAPE ART, INC for Avondale Promenade Park - 5.37% over the original contract amount - DISTRICT C - KAMIN

Background:

RECOMMENDATION: The General Services Department recommends approval of the final contract amount of $904,385.00 and acceptance of work on a contract with Landscape Art, Inc. for Avondale Promenade Park – 5.37% over the original contract amount.

 

SPECIFIC EXPLANATION: The General Services Department recommends that City Council approve the final contract amount of $904,385.00, accept the work and authorize final payment to Landscape Art, Inc. for construction services in connection with Avondale Promenade Park, for the Houston Parks and Recreation Department.

 

PROJECT LOCATION:  424 Westheimer, Houston, TX.

 

PROJECT DESCRIPTION: The project scope installed a craftsman style pavilion with chimney, brick landscape walls, ornamental lights with brick column bases; a promenade with inlaid bricks and concrete bands, concrete sidewalks, workout station, play component, dog run, site furnishing including seating, drinking fountain and trash receptacles; park signs; interpretive sign; fencing; underground drainage; electrical service; and landscaping and irrigation.

 

White Oak Studio was the design consultant for this project.

 

CONTRACT COMPLETION AND COST: The contractor completed the project within 365 days: the original contract time of 270 days, plus 95 days approved by Change Orders.  The final cost of the project, including Change Orders, is $904,385.00, an increase of $46,053.00 over the original contract amount.

 

PREVIOUS CHANGE ORDERS:  Change Order Nos. 1 – 6 removed 510 cubic yards of existing soil, removed a cypress tree which was in poor condition, added a concrete apron to the alleyway adjacent to the site, installed a 20 foot galvanized electrical pole for CenterPoint’s drop, removed 19 linear feet of duct bank from the contract, increased the mow band height, changed the one sided sign to a two sided sign, installed a landscape drain in the planting bed, added a 9 linear foot wrought iron electrical enclosure, added two granite remembrance plaques, and added non-compensable days due to Covid impacts and storm events.

 

M/WBE PARTICIPATION:  No City MWBE participation goal was established for this project as the contract amount does not exceed the threshold of $1,000,000.00 required for goal-oriented contracts per Section 15-82 of the City Code of Ordinances.

 

WBS No:  F-COC001-0001-4

 

 

 

 

 

DIRECTOR'S SIGNATURE / DATE

 

 

 

__________________________________

C. J. Messiah, Jr.

General Services Department

 

 

 

__________________________________

Kenneth Allen, Interim Director

Houston Parks and Recreation Department

 

 

 

 

Prior Council Action:

Ordinance No. 2019-910; November 20, 2019

Amount and Source of Funding:

 No Additional Funding Required

 

 Previous Funding

 

$     14,000.00             Parks & Recreation Dedication Fund (4035)

$   960,166.00             State – Grant Funded (5010) – Texas Parks and Wildlife Department

$   974,166.00             Total Funding

 

 

Contact Information:

Enid M. Howard

Council Liaison

Phone:  832.393.8023

 

 

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
Maps Backup Material