CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/5/2021
ALL
Item Creation Date: 6/17/2021

HPW - 20SWM52 - Contract Award / DL Glover, Inc.

Agenda Item#: 21.


 
                               
Summary:

ORDINANCE appropriating $3,540,000.00 out of Dedicated Drainage and Street Renewal Capital Fund - Drainage Charge, awarding contract to DL GLOVER, INC for FY2021 Drainage Rehabilitation Storm Water Action Team (SWAT) Work Orders No. 3; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for engineering and testing services and CIP Cost Recovery relating to construction of facilities financed by the Dedicated Drainage and Street Renewal Capital Fund – Drainage Charge

Background:

SUBJECT: Contract Award for FY2021 Drainage Rehabilitation, Storm Water Action Team, Work Orders #3 / DL Glover, Inc.

 

RECOMMENDATION: (SUMMARY) Accept low bid, award a Construction Contract for FY2021 Drainage Rehabilitation, Storm Water Action Team, Work Orders #3 to DL Glover, Inc. and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project will provide work authorizations on a location by location basis, as needed, for repair, rehabilitation or reconstruction of the storm water drainage assets to such a condition that they may be effectively used for its designated functional purpose.

 

DESCRIPTION/SCOPE: This citywide program provides construction services to resolve emergency localized storm water drainage problems. The project scope is established by each work authorization. The contract duration for this project is 730 calendar days.

 

LOCATION: The projects are located throughout the City of Houston (City).

 

BIDS:  The contract was advertised for bidding on January 29, 2021. Bids were received on February 18, 2021.  The six (6) bids are as follows:

 

 

Bidder

Adjustment Factor

1.

DL Glover, Inc.

0.799

2.

Reliance Construction Services, LP

0.839

3.

PM Construction & Rehab, LLC. dba IPR South Central

0.843

4.

J Rivas Construction, LLC

0.909

5.

Nerie Construction, LLC

0.920

6.

JFT Construction, Inc.

1.017

 

AWARD: It is recommended that this construction contract be awarded to DL Glover, Inc., with a low bid of $3,300,000.00 (0.799 Adjustment Factor).

 

PROJECT COST: The total cost of this project is $3,540,000.00 to be appropriated as follows:

 

  • Bid Amount

$3,300,000.00

  • Testing Services

$75,000.00

  • CIP Cost Recovery

$165,000.00

 

Testing Services will be provided by Alliance Laboratories, Inc. under a previously approved contract.

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case, DL Glover Inc., is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 7% MBE goal and 2% WBE goal for this project.

 

 

 

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

J. Rivas Construction LLC

Waterline, Sanitary Sewer and Drainage Improvements, Pavement Replacement

$181,500.00

5.50%

2.

T. Gray Utility & Rehab Co., LLC

Waterline and Sanitary Sewer

$49,500.00

1.50%

 

 

TOTAL

$231,000.00

7.00%

 

WBE – Name of Firms

Work Description

Amount

% of Contract

1.

Access Data Supply, Inc.

RCP, Manholes, Inlets Cement, Sand and Other materials

$66,000.00

2.00%

 

 

TOTAL

$66,000.00

2.00%

 

FISCAL NOTE:  No significant Fiscal Operating Impact is anticipated as a result of this project.

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. M-430006-0012-4

Amount and Source of Funding:

$3,540,000.00 from Fund No. 4042 – Dedicated Drainage and Street Renewal Capital Fund - Drainage Charge

Contact Information:

Tanzeem Chowdhury, Project Manager

Stormwater Operations

Transportation & Drainage Operations

P: 832-395-2820

E: Tanzeem.chowdhury@houstontx.gov