SUBJECT: Contract Award for FY2021 Drainage Rehabilitation Storm Water Action Team (SWAT) Work Orders No. 1.
RECOMMENDATION: (SUMMARY) Accept low bid, award construction contract for FY2021 Drainage Rehabilitation Storm Water Action Team (SWAT) Work Orders No. 1 to JFT Construction, Inc., with a maximum contract amount not to exceed $2,200,000.00 and allocate funds.
PROJECT NOTICE/JUSTIFICATION: This project will provide work authorizations on a location by location basis, as needed, to repair, rehabilitate or reconstruct the storm water drainage assets to such a condition that they may be effectively used for its designated functional purpose.
DESCRIPTION/SCOPE: This Citywide program provides construction services to resolve emergency localized storm water drainage problems. The project scope is established by each work authorization. The contract duration for this project is 730 calendar days.
LOCATION: The projects are located throughout the City of Houston (City).
BIDS: The contract was advertised for bidding on August 21, 2020. Bids were received on September 10, 2020. The eight (8) bids are as follows:
|
|
|
Bidder
|
|
Adjustment Factor
|
1.
|
|
|
JFT Construction, Inc.
|
0.747
|
2.
|
|
|
DL Glover, Inc.
|
|
0.785
|
3.
|
|
|
PM Construction & Rehab, LLC. dba IPR South Central
|
|
0.865
|
4.
|
|
|
T Construction, LLC.
|
|
0.866
|
5.
|
|
|
Grava, LLC.
|
|
0.870
|
6.
|
|
|
Reliance Construction Services, LP
|
|
0.932
|
7.
|
|
|
Total Contracting Limited
|
|
0.950
|
8.
|
|
|
Resicom, Inc.
|
|
1.250
|
AWARD: It is recommended that this construction contract be awarded to JFT Construction, Inc. with a low bid of $2,200,000.00 (0.747 Adjustment Factor).
PROJECT COST: The total cost of this project is $2,260,000.00 to be allocated as follows:
· Bid Amount
|
$2,200,000.00
|
· Testing Services
|
$60,000.00
|
|
|
Testing Services will be provided by Ninyo & Moore, Inc., under a previously approved contract.
HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case, JFT Construction, Inc., is a designated HHF company, but they were the successful awardee without application of the HHF preference.
PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.
M/WBE PARTICIPATION: The contractor has submitted the following proposed plan to satisfy the 7% MBE goal and 2% WBE goal for this project.
|
MBE - Name of Firms
|
Work Description
|
Amount
|
% of Contract
|
1
|
Professional Traffic Control, LLC
|
Flagging / Traffic Control
|
$110,000.00
|
5.00%
|
|
|
|
|
|
2
|
Joachim Trucking, Inc.
|
Pre-cast Concrete Pipe
|
$44,000.00
|
2.00%
|
|
|
|
|
|
|
|
SUBTOTAL:
|
$154,000.00
|
7.00%
|
|
SBE – Name of Firms
|
|
|
|
3
|
C. Sanchez Trucking
|
Hauling / Trucking
|
$44,000.00
|
2.00%
|
|
|
SUBTOTAL:
|
$44,000.00
|
2.00%
|
|
|
CONTRACT TOTAL:
|
$198,000.00
|
9.00%
|
Fiscal Note: Funding for this item is included in the FY21 Adopted Budget. Therefore, no Fiscal Note is required as stated in the Financial Policies.
_________________________________
Carol Ellinger Haddock, P.E., Director
Houston Public Works
WBS No. M-430006-0010-4