Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/6/2020
ALL
Item Creation Date:

HPW-20SWM28 Contract Award / Grava, LLC

Agenda Item#: 37.


 
                               
Summary:

ORDINANCE appropriating of $3,425,000.00 out of Dedicated Drainage and Street Renewal Capital Fund - Drainage Charge, awarding contract to GRAVA, LLC for FY2021 Local Drainage Program (LDP) Contract #1; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for testing services, contingency, and CIP Cost Recovery relating to construction of facilities financed by the  Dedicated Drainage and Street Renewal Capital Fund - Drainage Charge

Background:

SUBJECT: Contract Award for FY2021 Local Drainage Program (LDP) Contract #1.

 

RECOMMENDATION: (SUMMARY) Award a Construction Contract to Grava, LLC, for FY2021 Local Drainage Program (LDP) Contract#1 and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the Transportation & Operations Program and will provide work authorization on a location by location as needed, to preserve, repair, rehabilitate or reconstruct the storm water drainage asset to such a condition that it may be effectively used for its designated functional purpose.

 

DESCRIPTION/SCOPE: This Citywide program provides construction services to resolve localized storm water drainage problems. The scope is established by each work authorization. The contract duration for this project is 730 calendar days.

 

LOCATION: The projects are located throughout the City of Houston (City).

BIDS:  The project was advertised for bidding on July 17, 2020. Bids were received on August 6, 2020.  The eight (8) bids are as follows:

 

 

 

Bidder

 

Adjustment Factor

 

 

1.

Grava, LLC

0.760

2.

DL Glover, Inc.

0.763

3.

JFT Construction, Inc.

0.793

4.

Reliance Construction Services, LP.

0.841

5.

Nerie Construction

0.865

6.

PM Construction & Rehab, LLC

0.867

7.

Total Contracting Limited

0.890

8.

T. Construction LLC

0.918

 

 

AWARD: It is recommended that this construction contract be awarded to Grava, LLC with a low bid of $3,000,000.00 (0.760 Adjustment Factor).

 

PROJECT COST: The total cost of this project is $3,425,000.00 to be appropriated as follows:

 

· Bid Amount

$3,000,000.00

· Contingency (5%)

· CIP Cost Recovery

$150,000.00

$150,000.00

· Testing Services

$125,000.00

 

 

 

 

 

Testing Services will be provided by HVJ Associates, Inc. under a previously approved contract.

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case Grava, LLC is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 7% MBE goal and 2% WBE goal for this project.

 

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

 

 

 

 

 

1.

Juarez Mowing

Landscape care and

maintenance services

$195,000.00

6.50%

2.

Wilson Flagging Control

Flagging (i.e. traffic control)

services

$ 15,000.00

0.50%

 

 

TOTAL:

$210,000.00

7.00%

 

WBE - Name of Firms

 

 

 

1.

J.A. Gamez Trucking Services.

Trucking, specialized freight

(except used goods)

$60,000.00

2.00%

TOTAL:

$60,000.00

2.00%

 

 

CONTRACT TOTAL:

$270,000.00

9.00%

                                   

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

 

 

 

_________________________________

Carol Ellinger Haddock, P.E.

Director

Houston Public Works

 

WBS No. M-420126-0116-4

Amount and Source of Funding:

$3,425,000.00 from Fund No. 4042 – Dedicated Drainage and Street Renewal Capital Fund-Drainage Charge

 

Contact Information:

Bryan Gropp, Project Manager

Transportation & Drainage Operations

P: 832-395-2965

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapBackup Material
2020-873 Executed OrdinanceOrdinance/Resolution/Motion