Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/29/2020
ALL
Item Creation Date: 8/11/2020

HPW-20PMO14, Construction Contract Award / Tikon Group, Inc.

Agenda Item#: 36.


 
                               
Summary:

ORDINANCE appropriating $1,459,937.76 out of Metro Projects Construction-DDSRF, awarding contract to TIKON GROUP, INC for Citywide Work Orders for Council District Service Fund Project #5; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for testing services, CIP Cost Recovery and contingencies relating to construction of facilities financed by the Metro Projects Construction-DDSRF

Background:

SUBJECT: Contract Award for Citywide Work Orders for Council District Service Fund Project # 5

 

RECOMMENDATION: (SUMMARY) Accept low bid, award construction contract to Tikon Group, Inc., for Citywide Work Orders for Council District Service Fund Project # 5 and appropriate funds.

PROJECT NOTICE/JUSTIFICATION:  This project is part of the Street and Traffic Control Capital Improvement Plan (CIP) and is required to meet current City of Houston Standards as well as improve sidewalks, street surfaces, curbs, mobility and safety at intersections. The work orders will be determined by the Council District Service Fund (CDSF) process.

DESCRIPTION/SCOPE: This contract consists of rebuilding sidewalks, panel replacements, overlays, curb-ramps, pavement markings, signing and other work to be detailed on the plans. The contract duration for this project is 365 days.

 

LOCATION: The projects are located throughout the City of Houston (City).

 

BIDS: This project was advertised for bidding on March 20, 2020 and on March 27, 2020. The Bids were received on April 2, 2020. The five (5) bids are as follows:

 

 

Bidder

                                      Bid Amount

1.

Tikon Group, Inc.

$1,290,852.50

2.

DCE Construction, Inc.

$1,493,474.20

3.

T Construction, Inc.

$1,888,881.00

4.

5.

 

Total Contracting Limited

Skylar Design Build, LLC

 

$2,227,435.00

$2,181,128.35

 

AWARD: It is recommended that this construction contract be awarded to Tikon Group, Inc. with a low bid of $1,290,852.50

 

PROJECT COST: The total cost of this project is $1,459,937.76 to be appropriated as follows:

 

Bid Amount

$1,290,852.50

Contingencies

$64,542.63

Testing Services

$40,000.00

CIP Cost Recovery

$64,542.63

 

 

Testing Services will be provided by A&R Engineering & Testing Inc. under a previously approved contract.

 

The appropriations for CIP Cost Recovery are necessary to fund project management costs but will not be charged to CDSF.

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case, Tikon Group, Inc. is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 12% MBE goal and 7% WBE goal for this project.

 

 

MBE - Name of Firms

1. Unotec Construction Company

 

2. U.S. Ready Mix, Inc.

 

 

 

 

WBE – Name of Firms

1. TANCOE

 

 

 

 

SBE – Name of Firms

1. Fabco LLC

Work Description

Concrete Services

 

Ready Mix Concrete

 

TOTAL

 

 

Work Description

Traffic Control/Flaggers

 

TOTAL

 

 

Work Description

Construction Supplies

 

TOTAL

 

 

Contract Total

Amount

$ 129,085.25

 

$ 51,634.10

 

$180,719.35

 

 

Amount

$ 51,634.10

 

$ 51,634.10

 

 

Amount

$ 51,634.10

 

$ 51,634.10

 

 

$283,987.55

% of Contract

10.00%

 

4.00%

 

14.00%

 

 

% of Contract

4.00%

 

4.00%

 

 

% of Contract

4.00%

 

4.00%

 

 

22.00%

 

 

 

 

 

 

FISCAL NOTE:  No significant fiscal operating impact is anticipated as a result of this project.

 

 

 

 

 

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. N-322017-0013-4


Amount and Source of Funding:

$ 1,459,937.76 Fund No. 4040 METRO Projects Construction – DDSRF


Contact Information:

Michael T. Wahl, P.E., PTOE

Assistant Director, Transportation and Drainage Operations

Phone: (832) 395-2443


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapBackup Material
2020-843 Executed OrdinanceOrdinance/Resolution/Motion