CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 8/18/2020
District B
Item Creation Date: 7/20/2020

HPW – 20MEM33 Contract Award / Harper Brothers Construction, LLC

Agenda Item#: 42.


 
                               
Summary:

ORDINANCE appropriating $30,816,338.81 out of Water & Sewer System Consolidated Construction Fund, awarding contract to HARPER BROTHERS CONSTRUCTION LLC for North Corridor Consolidation Package 1; Northgate Regional Pump Station-37 MGD Lift Station and Force Mains; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for testing services, CIP Cost Recovery, construction management and contingencies relating to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund - DISTRICT B - DAVIS

Background:

SUBJECT: Contract Award for North Corridor Consolidation Package 1; Northgate Regional Pump Station – 37 MGD Lift Station at Northgate and Force Mains.

 

RECOMMENDATION:  Award a Construction Contract to Harper Brothers Construction, LLC for North Corridor Consolidation Package 1; Northgate Regional Pump Station – 37 MGD Lift Station at Northgate and Force Mains and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION:  This project is part of the City’s Capital Improvement Plan (CIP) Consolidation Package for wastewater facilities.

 

The work to be performed under this contract award is necessary to maintain compliance with Houston's proposed wastewater consent decree with EPA and TCEQ.

 

DESCRIPTION/SCOPE: This project consists of the construction of the Northgate Regional Pump Station (RPS) with a firm capacity of 37 MGD with wet pit/dry pit configuration and 24-inch/30-inch dual force mains to discharge to a 54-inch gravity interceptor being constructed under separate projects. The Contract duration for this project is 640 calendar days. This project was designed by CH2M Hill, Inc.

 

LOCATION: The project area is generally bound by Greens Road on the north, Beltway 8 on the south, Hardy Toll Road on the east and I-45 North on the west.

 

BIDS: This project was advertised for bidding on March 6, 2020. Bids were received on April 9, 2020.  The seven (7) bids are as follows:

 

 

Bidder

       Bid Amount

1.

Harper Brothers Construction, LLC

$25,937,120.70

2.

SER Construction Partners LLC

$31,385,290.30

3.

Triple B Services, LLP

$31,870,515.85

4.

LEM Construction Company, Inc.

$32,377,395.00

5.

Thalle Construction Co. Inc.

$32,781,805.00

6.

BRH-Garver Construction, L.P.

$33,837,654.00

7.

Boyer, Inc.

$37,879,748.00

 

AWARD: It is recommended that this construction contract be awarded to Harper Brothers Construction, LLC with a low bid of $25,937,120.70 and Addenda Numbers 1, 2 and 3 be made a part of this Contract.

 

PROJECT COST: The total cost of this project is $30,816,338.81 to be appropriated as follows:

 

· Bid Amount

$25,937,120.70

· Contingencies

$1,296,856.04

· Testing Services

$300,000.00

· CIP Cost Recovery

$2,593,712.07

· Construction Management

$688,650.00

 

Testing Services will be provided by Alliance Laboratories, Inc., under a previously approved contract.

 

Construction Management Services will be provided by Briones Consulting & Engineering LTD under a previously approved contract.

 

 

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case, Harper Brothers Construction, LLC, is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WSBE PARTICIPATION:  The project primarily involves pipeline and facilities work. Harper Brothers Construction (Prime) has listed the firms below to achieve the 13% MBE goal and the 7% WBE goal on this project. MWSBE participation will be achieved by using 1st and 2nd tiered subcontractors as allowed in the MWBE Program. In addition to the six (6) 1st tiered MWSBE subcontractors listed for participation, Peltier Brothers, a non-certified firm, will be a 1st tier subcontractor to the Prime. Peltier Brothers will subcontract some of their work to four (4) 2nd tiered MWSBE certified firms to perform facilities work on the contract and the Prime will receive MWSBE credit for dollars paid to those 2nd tier subcontractors.  

 

Harper Brothers Construction, LLC:

Subcontractors

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

Ikon Environmental Solutions, LP

Environmental Services

$33,718.26

0.13%

2.

Karami Plumbing and Construction Supply LLC

Pipe Waterline Supplier

$2,059,407.33

7.94%

3.

Reliable Signal & Lighting Solutions, LLC

Electrical Services

$277,527.19

1.07%

4.

Wilson Flagging Control

Flaggers

$145,247.87

0.56%

 

 

TOTAL

$2,515,900.65

9.70%

 

 

WBE - Name of Firms

Work Description

Amount

% of Contract

1.

KMA Contractors Services Inc.

Inlets & Pipe Supplier

$534,304.67

2.06%

2.

MVA Construction LLC

Paving

$119,310.75

0.46%

 

 

TOTAL

$653,615.42

2.52%

 

 

SBE - Name of Firms

Work Description

Amount

% of Contract

1.

Gulf Coast Grouting, Inc.

Grouting

$199,715.82

0.77%

2.

Highway 1 LLC

Striping

$94,770.25

0.37%

3.

K4 Environmental LLC

Storm Water Pollution Prevention Plan

$48,881.65

0.19%

4.

National Works, Inc.

Manhole Coating

$285,631.00

1.10%

5.

R. Ortiz Trucking

Trucking

$246,402.64

0.95%

 

 

TOTAL

$875,401.36

3.38%

 

 

Peltier Brothers Construction, Ltd. (Non-MWSBE Firm)

2nd Tier Subcontractors:

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

C & B Rebar Construction, Inc.

Supply & Install Rebar

$841,541.00

3.24%

2.

DTI A-Group, LLC, DBA McCrory Engineering

Furnish & Install Lift Station Site Paving

$83,300.00

0.32%

 

 

TOTAL

$924,841.00

3.56%

 

 

WBE - Name of Firms

Work Description

Amount

% of Contract

1.

F & L Coatings And Concrete, L.L.C.

Supply & Apply Coatings

$311,500.00

1.20%

 

 

TOTAL

$311,500.00

1.20%

 

 

SBE - Name of Firms

Work Description

Amount

% of Contract

1.

Automation Nation, Inc..

Furnish & Install Software Engineering

$19,200.00

0.07%

 

 

TOTAL

$19,200.00

0.07%

 

 

 

 

Total MWSBE participation plan:

   Amount  % of Contract
 MBE $3,440,741.65  13.26%
 WBE $965,115.42  3.72%
 SBE  $894,601.36  3.45%
 GRAND TOTAL    $5,300,458.43 20.43% 

 

 

 

FISCAL NOTE:  No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. R-000536-0008-4

Amount and Source of Funding:

$30,816,338.81

Water and Sewer System Consolidated Construction Fund

Fund No. 8500

Contact Information:

R. Jeff Masek

Assistant Director, Capital Projects

Phone: (832) 395-2387