Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 3/24/2020
District B
Item Creation Date: 2/5/2020

HPW – 20VNP65 Contract Award / Harper Brothers Construction LLC

Agenda Item#: 59.


 
                               
Summary:

O 2020-0237 ORDINANCE authorizing the transfer of $12,892,303.61 from NETL Expansion-Swift Fund to the HPW-NETL Construction Fund and appropriating said sum out of HPW-NETL Construction Fund, appropriating $17,321,672.52 out of Water Authorities Capital Contribution-NETL Fund, appropriating $4,039,323.87 out of Water & Sewer System Consolidated Construction Fund, awarding contract to HARPER BROTHERS CONSTRUCTION, LLC for 108-inch Water Line along City easements from Imperial Valley Drive to Green Plaza Drive; setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for testing services, CIP Cost Recovery, Construction Management, Construction Program Management Services, and contingencies relating to construction of facilities financed by the HPW-NETL Construction Fund, Water Authorities Capital Contribution-NETL Fund, and Water & Sewer System Consolidated Construction Fund

Background:

SUBJECT:  Contract Award for 108-inch Water Line along City Easements from Imperial Valley Drive to Green Plaza Drive.

 

RECOMMENDATION:  Award a Construction Contract to Harper Brothers Construction LLC for 108-inch Water Line along City Easements from Imperial Valley Drive to Green Plaza Drive and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION:  This project is part of the City's Surface Water Transmission program and supports the execution of the Northeast Transmission Line project from the Northeast Water Purification Plant to the Water Authorities take-points for the Infrastructure Capital Improvement Plan.  It is required to improve existing water distribution systems and to meet Harris-Galveston Coastal Subsidence Districts Legislative mandate to regulate the withdrawal of groundwater.  The project is a combination of water line construction, public utility adjustments, sidewalk and roadway pavement replacement.

 

DESCRIPTION/SCOPE:  This project consists of the construction of approximately 6,300 linear feet of 108-inch, 50 linear feet of 84-inch, 90 linear feet of 66-inch, 80 linear feet of 24-inch transmission lines, 380 linear feet of 16-inch and 1,600 linear feet of 12-inch distribution water lines, roadway reconstruction with sidewalk replacement and limited storm sewer/inlet replacement.   The Contract duration for this project is 575 calendar days. This project was designed by  KUO & Associates, Inc. and Lockwood, Andrews & Newnam, Inc.

 

LOCATION:  This project is along Esplanade Boulevard, Plaza Verde Drive, and City Easements from Imperial Valley Drive to Green Plaza Drive.

 

PROPOSALS:  This project was advertised for competitive sealed proposals on October 11, 2019. Proposals were received on November 21, 2019.  The five (5) bids as part of the proposals received are as follows:

 

 

Proposer

Proposal Bid Amount

1.

Harper Brothers Construction LLC

$29,707,898.50

2.

Main Lane Industries, Ltd.

$33,738,414.75

3.

Thalle Construction Co., Inc.

$34,807,528.00

4.

S.J. Louis Construction of Texas, Ltd.

$34,847,335.73

5.

Boyer, Inc.

$38,691,434.00

 

AWARD:  A Selection Committee was comprised of members from Houston Public Works and Houston Airport System. The Selection Committee reviewed the proposals and recommended that this construction contract be awarded to Harper Brothers Construction LLC based on their Financial Capabilities, Experience, prior MWSBE Compliance, Safety Record, Key Personnel, Team Structure, Schedule, QA/QC, Project Controls, Litigation, Environmental, and Hire Houston First Designation with a total proposal bid price of $29,707,898.50 and that Addenda Numbers 1 and 2 be made a part of this Contract.

 

PROJECT COST:  The total cost of this project is $34,253,300.00 to be appropriated as follows:

 

· Proposal Bid Amount

$ 29,707,898.50

· Contingencies

$   1,628,487.32

· Testing Services

$      410,000.00

· CIP Cost Recovery

$      891,291.18

· Construction Program Management Services

$      547,465.00

· Construction Management

$   1,068,158.00

 

Testing Services will be provided by Terracon Consultants, Inc. under a previously approved contract.

 

Construction Program Management Services will be provided by KCI Technologies, Inc. under a previously approved contract.

 

Construction Management Services will be provided by Stantec Consulting Services, Inc. under a previously approved contract.

 

 

HIRE HOUSTON FIRST:  The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case, Harper Brothers Construction LLC is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM:  The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WSBE PARTICIPATION:  The contractor has submitted the following proposed program to satisfy the 12% MBE goal and 7% WBE goal for this project.

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

MVA Construction LLC

Concrete paving

$1,128,900.15

  3.80%

2.

Wilson Flagging Control

Flaggers

$   297,078.99

  1.00%

3.

Karami Plumbing and Construction Supply LLC

Plumbing

$1,544,810.72

  5.20%

4.

R. Ortiz Trucking

Trucking

$   594,157.97

  2.00%

 

 

TOTAL

$3,564,947.83

12.00%

 

 

WBE - Name of Firms

Work Description

Amount

% of Contract

1.

H&E Aggregate, L.L.C.

Sand

$   386,202.68

  1.30%

2.

KMA Contractors Services Inc.

Reinforced concrete box and pipe

 

$   742,697.46

 

  2.50%

 

 

TOTAL

$1,128,900.14

  3.80%

 

 

SBE - Name of Firms

Work Description

Amount

% of Contract

1.

GMJ Paving Company LLC

Asphalt

$      35,625.00

 0.12%

2.

Contractors Paving Supply, LLC

Paving accessories

$    148,539.49

 0.50%

3.

IKON Environmental Solutions, LP

Environmental

$    437,048.75

1.47%

4.

Gulf Coast Grouting, Inc.

Grouting

$    146,000.00

0.49%

5.

Traffic Systems Construction, Inc.

Electrical

$      36,579.00

0.12%

6.

Mickie Service Company, Inc.

Tapping sleeve and valve

$      54,425.00

0.18%

7.

Professional Traffic Control LLC

Traffic Control

$    101,000.00

____________

 0.34%

______

 

 

TOTAL

$    959,217.24

 3.22%

 

FISCAL NOTE:  No significant Fiscal Operating impact is anticipated as a result of this project.

 

There is a total of four (4) parcels.  One (1) parcel has been acquired, and the remaining three (3) pending parcels will be acquired before the end of March 2020.

 

All utility relocations will be completed upon parcel acquisitions.  

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. S-000900-0168-4

Amount and Source of Funding:

Total: $34,253,300.00

 

$4,039,323.87 from Fund No. 8500 – Water and Sewer System Consolidated Construction Fund

 

$17,321,672.52 from Fund No. 8507 - Water Authorities Capital Contribution-NETL Fund

 

$12,892,303.61 transfer from Fund No. 8426 – NETL Expansion – SWIFT into Fund No. 8508 – HPW -NETL Construction Fund and Appropriate from Fund No. 8508 – HPW-NETL Construction Fund

Contact Information:

R. Jeff Masek, P.E., CCM

Assistant Director, Capital Projects

Phone: (832) 395-2387