CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 2/11/2020
District J, District K
Item Creation Date: 1/9/2020

HPW – 20EN43 Accept Work / Industrial TX Corp.

Agenda Item#: 3.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $10,274,901.24 and acceptance of work on contract with INDUSTRIAL TX CORP. for Keegans Bayou and Greenridge Wastewater Treatment Plant Improvements - 8.41% under the original contract amount  DISTRICTS J - POLLARD and K - CASTEX-TATUM


Background:

SUBJECT:  Accept Work for Keegans Bayou and Greenridge Wastewater Treatment Plant Improvements.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $10,274,901.24 or 8.41% under the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s program to renew/replace inefficient components of the existing Wastewater Treatment Plant Facilities.

 

DESCRIPTION/SCOPE: This project consisted of design of various components of the subject wastewater treatment plant facilities. Infrastructure Associates, Inc. designed the project with 800 calendar days allowed for construction. The project was awarded to Industrial TX Corp. with an original Contract Amount of $11,218,270.00.

 

LOCATION: The project area is located at the following addresses:

  

  Location  Address  Council District 
1.  Keegans Bayou WWTP        9400 White Chapel Ln.       J
2. Greenridge WWTP 6301 #1 W. Fuqua K

 

CONTRACT COMPLETION AND COST: The Contractor, Industrial TX Corp., has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 389 days approved by Change Order Nos. 4, 5, 6, and 7.  The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos. 1, 2, 3 and 5 is $10,274,901.24, a decrease of $943,368.76 or 8.41% under the original Contract Amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised M/WBE contract goal for this project was 18.00%.  The M/WBE plan established for this project was 35.79%.  According to Office of Business Opportunity, the participation was 39.55%. Contractor’s M/WBE performance evaluation was rated Outstanding.

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. R-000265-0079-4

Prior Council Action:

Ordinance No. 2016-0040, dated 01-13-2016

Amount and Source of Funding:

No additional funding required.

 

Total (original) appropriation of $13,235,750.00 from Fund 8500 - Water and Sewer System Consolidated Construction Fund.

Contact Information:

R. Jeff Masek, P.E., CCM

Assistant Director, Capital Projects

Phone: (832) 395-2387

 

 

 

 

 

 