RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $1,538,568.33 and acceptance of work on contract with T CONSTRUCTION LLC for Wastewater Collection System Rehabilitation and Renewal - 1.12% under the original contract amount - DISTRICTS A - PECK; B - DAVIS; C - KAMIN; D - EVANS-SHABAZZ; F - THOMAS; H - CISNEROS; I - GALLEGOS and K - CASTEX-TATUM

Background:

SUBJECT: Accept Work for Wastewater Collection System Rehabilitation and Renewal.

 

RECOMMENDATION: (Summary) Pass a motion to approve the final contract amount of $1,538,568.33, which is 1.12% under the original contract amount, accept the work, and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: Under this project, the contractor provided sewer point repairs, pipe replacement and pipe bursting to deteriorated sewer collection systems throughout the City.

 

DESCRIPTION/SCOPE: This project consisted of sanitary sewer point repairs, pipe replacement and pipe bursting. The project was awarded to t constructionwith an original contract amount of $1,555,962.95. The Notice to Proceed date was 06/25/2015 and the project had 730 calendar days for completion.

 

LOCATION: This work order project was located at various locations within Council Districts A, B, C, D, F, H, I and K.

 

CONTRACT COMPLETION AND COST: The contractor, T Construction, LLC, has completed the work under the contract. The contract was completed within the contract time. The final cost of the project is $1,538,568.33, a decrease of $17,394.62 or 1.12% under the original contract amount. Less point repairs and pipe replacement were needed than anticipated.

 

The final amount of this work order contract was not affected by Change Orders No. 1, No. 2, No. 4, No. 5, No. 6, No. 7, No. 8 and No. 9.           

 

MWDBE PARTICIPATION:  The MWDBE goal for this project was 22.53%. According to the Office of Business Opportunity, the actual participation was 25.25%. The contractor was awarded an “Satisfactory” rating from the Office of Business Opportunity.

 

                                               

Carol Ellinger Haddock, P.E.

Director

Houston Public Works

 

WBS# R-000266-0217-4

File No. 4235-77

Prior Council Action:

Ordinance No. 2014-1170 dated 12/17/2014

Amount and Source of Funding:

No additional funding required.

 

 

Original appropriation of $1,663,761.00 for construction and contingencies from Water and Sewer System Consolidated Construction Fund No. 8500.